Follow the records that carry an airfield lighting project from BOQ and submittals through inspection and test plans, as-built drawings, commissioning reports, O&M manuals, snag lists and final handover.

Overview

AGL Project Documentation

Airfield Ground Lighting (AGL) projects require coordinated engineering, commercial, quality, inspection, testing and handover documentation. Complete and traceable records help demonstrate that the installed system follows the approved design and that the required inspections and tests have been performed.

Project documentation also supports communication between contractors, consultants, airport authorities, suppliers, installation teams and maintenance personnel.

The exact documentation requirements depend on the contract, airport requirements, project scope, applicable standards, approved procedures and authority approval process.

Documents covered in this guide

Project planBOQ & specificationsTechnical submittalsITPQuality recordsAs-built & redline drawingsTest & commissioning reportsO&M manualsSnag listProgress & riskHandover checklistDocument control
1 · Planning & Execution

AGL Project Planning and Execution

An AGL project plan establishes the scope, sequence of work, responsibilities, resources, inspection requirements, material approvals and interfaces needed to complete the installation.

A typical project execution sequence may include

01

Review the contract, technical specifications and approved drawings.

02

Conduct a site survey and verify existing infrastructure.

03

Prepare the Bill of Quantities (BOQ) and material requirements.

04

Submit equipment datasheets, technical documents and samples for approval, where required.

05

Plan civil, electrical, cabling and equipment installation activities.

06

Carry out inspections and tests at the specified stages.

07

Complete functional testing and commissioning.

08

Record outstanding items and close the punch list.

09

Compile final documentation and prepare handover records.

The actual sequence must follow the approved construction methodology, project programme, airport access restrictions and operational requirements.

Key project planning documents

Project execution planApproved project programmeScope of work and responsibility matrixApproved drawings and technical specificationsMaterial submittal registerBOQ and procurement scheduleInspection and test planQuality plan and risk registerProgress reports and meeting records
Engineering objective: Establish clear responsibilities, approval stages and records before work begins.
2 · BOQ & Specifications

AGL BOQ and Technical Specifications

The Bill of Quantities (BOQ) identifies the equipment, materials, quantities and work items required for the project. It supports procurement, cost estimation, commercial evaluation, progress measurement and payment documentation according to the contract.

Typical AGL BOQ items

Runway, taxiway and approach light fittingsPAPI equipment and associated accessoriesConstant Current Regulators (CCRs)AGL isolating transformersPrimary series cablesPrimary connectors and jointing accessoriesSecondary leads and connectorsCable pits, ducts and related civil worksAirfield signs and control equipmentALCMS hardware, software and interfacesInstallation, testing and commissioningDocumentation, training and handover activities

What an AGL BOQ should contain

Each BOQ item should have a clear description, unit of measurement, quantity and relevant technical reference. Where applicable, it should identify the equipment rating, configuration, accessories and installation scope.

BOQ fieldPurpose
Item numberIdentifies the line item
Equipment descriptionDefines the product or work
Technical referenceLinks the item to the specification or drawing
UnitDefines how the item is measured
QuantityStates the required quantity
Unit rateRecords the applicable commercial rate
Total amountCalculates the extended value
RemarksRecords relevant assumptions or scope notes

Technical specification requirements

Specifications should define the required performance, dimensions, electrical ratings, materials, environmental conditions, testing requirements, applicable standards and documentation.

Avoid specifying equipment only by a generic product name when electrical, optical or performance characteristics are necessary for correct selection.

Before issuing a BOQ, verify that quantities and descriptions agree with the approved design, equipment schedules and scope of work.
3 · Submittals

Technical Submittals and Material Approval

Technical submittals provide evidence that proposed equipment and materials meet the specified project requirements.

An AGL material submittal may include

Manufacturer and product identificationModel number and equipment ratingTechnical datasheetProduct catalogue or technical drawingsApplicable compliance statementsType-test or routine-test documentation, where requiredInstallation and maintenance informationDeviations or exceptions against the specificationWarranty information, where applicable

Technical submittal workflow

01

Identify the applicable specification and drawing references.

02

Prepare the document package for the proposed product.

03

Check that the model, ratings and accessories match the project requirements.

04

Identify deviations clearly rather than leaving them implicit.

05

Submit the package through the designated approval process.

06

Record review comments and required revisions.

07

Track the final disposition and approved document revision.

08

Ensure the delivered equipment matches the approved submittal.

Approval of a datasheet should not be assumed to approve every aspect of installation, performance or commissioning. Follow the project’s formal approval process and acceptance criteria.
4 · ITP

AGL Inspection Test Plan (ITP)

An Inspection and Test Plan (ITP) defines the inspection and testing activities required at specified stages of a project. It identifies the responsible parties, inspection points, acceptance criteria and records to be retained.

An ITP helps ensure that critical activities are inspected at the correct stage and that the required evidence is available for review.

Typical ITP activities

Incoming material inspectionVerification of equipment identification and ratingsInspection of cable routes and installationCable joint and connector checksIsolating transformer installation checksFixture installation and mounting verificationCCR installation and equipment checksApplicable electrical testsCircuit continuity and functional checksControl and monitoring verificationPhotometric testing, where specifiedFinal inspection and handover documentation

Typical ITP fields

FieldDescription
ActivityWork or inspection being performed
ReferenceApplicable drawing, specification or procedure
Inspection methodVisual inspection, measurement or test
Acceptance criteriaRequired result or tolerance
ResponsibilityContractor, quality team, consultant or authority as applicable
Inspection pointHold, witness, review or other designated point
RecordForm, checklist, test report or inspection certificate
StatusPending, accepted, rejected or requiring corrective action
Inspection-point definitions and responsibilities must follow the project’s approved ITP. Do not assume that every project uses identical hold-point or witness-point requirements.
HOW REQUIREMENTS TRAVEL INTO TESTING 1 REQUIREMENT LIST Requirements that must be proved by measurement or operation OUTPUT: TEST ITEMS 2 TEST PLAN Test type, method, instruments and acceptance criteria OUTPUT: TEST PROCEDURES 3 PREPARE Calibrated instruments, isolation, permits and safe access OUTPUT: READY TO TEST 4 CARRY OUT TESTS Factory, site and commissioning tests OUTPUT: MEASURED RESULTS 5 EVALUATE Compare each result with its acceptance criterion OUTPUT: PASS, RETEST OR NON-CONFORMANCE 6 RECORD & CLOSE Signed records, matrix updated, items closed OUTPUT: TEST RECORDS FEEDBACK LOOP A failed test goes to investigation and repair, then back to retest; the acceptance criterion is never changed without formal approval. CRITERIA FIRST · THEN PREPARE, TEST, EVALUATE AND RECORD SIMPLIFIED SEQUENCE · FOLLOW YOUR SITE PERMIT AND ISOLATION PROCEDURE
Figure 1. How requirements flow into AGL testing: each requirement becomes a test with a method and acceptance criterion.AGL Visual Encyclopedia: How do requirements flow into AGL testing?
5 · Quality Plan

AGL Quality Plan and Inspection Records

The project quality plan defines how quality requirements will be implemented, checked, documented and controlled. It should identify inspection responsibilities, document control arrangements, calibration requirements, nonconformity handling and record retention.

Typical quality records

Incoming material inspection reportsApproved material submittalsInstallation inspection checklistsCable and connector inspection recordsElectrical test reportsCCR inspection and test recordsFunctional test reportsPhotometric reports, where requiredCalibration certificates for applicable test equipmentNonconformity reportsCorrective-action recordsFinal inspection and acceptance records

Managing nonconformities

When work or equipment does not meet the specified requirements, the issue should be recorded and handled through the approved nonconformity process.

A useful record identifies the affected item or location, the requirement that was not met, the observed condition, the responsible party, the corrective action and the verification of closure.

A nonconformity should not be marked closed until the required corrective action and verification have been completed.
DOCUMENTATION · THE INSPECTION IS NOT FINISHED UNTIL IT IS RECORDED RECORD AS FOUND · SIGN IT · NEVER ERASE 1 ASSET Asset ID, type Location, circuit RECORD FIELD 2 WHEN / WHO Date, time Inspector, method RECORD FIELD 3 FINDINGS As found, measured Instrument used RECORD FIELD 4 GRADE Condition grade Reason for it RECORD FIELD 5 PHOTOS Dated, located Before any work RECORD FIELD INSPECTION RECORD SIGNED · DATED · FILED IN THE ASSET REGISTER 6 TREND COMPARE · PLAN ACTION WORK ORDER RAISED EVIDENCE AUDIT · HANDOVER SCHEMATIC · EXAMPLE RECORD FIELDS ONLY · NOT TO SCALE
Figure 2. Inspection documentation: the signed record of what was inspected, found and decided.AGL Visual Encyclopedia: What is inspection documentation?
6 · As-Built Drawings

AGL As-Built Drawings and Redline Drawings

As-built documentation records the verified configuration of the installed system. It helps the airport team identify equipment, locate circuits, maintain the installation and plan future modifications.

Redline drawings

Redline drawings record changes made during construction. They may capture differences between the approved design and actual installation, including revised routes, equipment locations, cable arrangements or circuit identifiers. Redlines are working records and must be reviewed and incorporated into the final documentation process.

Final as-built drawings

The final as-built drawings should reflect the verified installed configuration and follow the project’s documentation requirements.

AGL as-built records may include

Lighting layout drawingsCircuit routes and identifiersPrimary cable schedulesEquipment locations and identification tagsCCR and associated circuit referencesTransformer and fixture detailsControl and monitoring interfacesRelevant cable pits, ducts and installation detailsApproved changes from the original design

As-built drawing workflow

01

Use the latest approved drawings as the baseline.

02

Record changes during execution.

03

Verify changes against the completed installation and available inspection records.

04

Update drawing references, equipment tags and circuit schedules.

05

Complete the required technical review.

06

Issue the final drawings with the appropriate revision and status.

07

Submit them in the formats specified by the contract.

Do not issue unverified redline markups as final as-built documentation. The final records must represent the installed configuration to the level required by the project.
AS-BUILT RECORDS AND CIRCUIT SCHEDULES · WHAT WAS ACTUALLY INSTALLED RECORD AS BUILT · SAME REFERENCES · KEEP CURRENT 1 MARK UP Red-line site changes Routes and positions Note every deviation STEP: record 2 VERIFY Survey routes and pits Match tags to drawing Confirm equipment STEP: check 3 REDRAW Update the drawings Same circuit references New revision issued STEP: issue 4 SCHEDULE List each circuit Cable, lights, load Add test values STEP: tabulate 5 APPROVE Compare with the site Check against design Sign and date STEP: confirm 6 HAND OVER Into asset register Linked to each asset Controlled copies out STEP: file EVERY REPAIR, RE-ROUTE OR UPGRADE LOOPS BACK: THE RECORDS ARE UPDATED, NOT LEFT BEHIND INPUTS RED-LINES · SURVEY · TESTS · EQUIPMENT DATA What the records are built from OUTPUT AS-BUILT SET · CIRCUIT SCHEDULES Baseline for tracing, testing and maintenance POOR RECORDS: WRONG CABLE TRACED · WRONG LOAD ASSUMED · SLOW FAULT FINDING SCHEMATIC · SIMPLIFIED · NOT TO SCALE · STEPS OVERLAP
Figure 3. As-built records and circuit schedules: what was actually installed, circuit by circuit.AGL Visual Encyclopedia: What are as-built records and circuit schedules?
7 · Test & Commissioning Reports

AGL Testing and Commissioning Reports

Testing and commissioning records demonstrate that specified inspection, electrical, functional and performance checks have been completed and documented. The exact tests and acceptance criteria depend on the equipment, project specification, approved procedures and applicable requirements.

Typical commissioning records

Pre-commissioning inspection checklistEquipment identification and rating verificationInstallation inspection reportsApplicable cable and electrical test recordsCCR functional test reportsSeries-circuit functional checksLight-fitting operation checksControl and monitoring verificationPhotometric test reports, where requiredDefect and corrective-action recordsFinal commissioning report

What a test report should contain

A test report should identify the equipment or circuit, location, date, test method, applicable acceptance criteria, test instruments, relevant calibration information, measured results, outcome and responsible personnel.

Where a test result does not meet the specified criteria, record the discrepancy and follow the approved corrective-action and retesting process.

Important: A completed checklist is not, by itself, proof that a system meets every performance requirement. Acceptance must be based on the applicable criteria and the required supporting evidence.
TEST DOCUMENTATION · THE WRITTEN EVIDENCE PLANNED · RECORDED · CHECKED · SIGNED · FILED 1 PLAN Test plan agreed Limits stated Sheets prepared RECORD: test plan 2 RECORD Values written live Date, time, tester Instrument noted RECORD: test sheets 3 VERIFY Within the limits Calibration current Nothing left blank RECORD: check 4 SIGN Tester signs Witness signs Engineer signs RECORD: sign-offs 5 FILE Report compiled Indexed, traceable In handover pack RECORD: test report RECORD COMPLETE? TRACEABLE · SIGNED · WITHIN LIMITS 6 INCOMPLETE OR UNCLEAR CORRECT · RE-TEST · RE-FILE COMPLETE READY FOR HANDOVER SCHEMATIC · STEPS SHORTENED · NOT TO SCALE
Figure 4. Test documentation: what was tested, how, with what, the result and who signed it.AGL Visual Encyclopedia: What is test documentation?
8 · O&M Manuals

AGL Operation and Maintenance (O&M) Manuals

An Operation and Maintenance (O&M) manual provides the information needed to operate, inspect and maintain the installed equipment. A project-specific manual should be suitable for the actual equipment and configuration supplied.

Typical O&M manual contents

System overview and equipment descriptionApproved system and connection drawingsEquipment schedules and identification detailsManufacturer operating instructionsInspection and preventive maintenance proceduresApplicable fault-finding guidanceSafety precautions and isolation requirementsReplacement component informationRecommended spare-parts listMaintenance and test record templatesWarranty informationManufacturer and service-support details

Why O&M manuals matter

A clear O&M manual helps maintenance teams understand the installed system, follow approved procedures, identify the correct equipment and maintain a consistent record of inspection and maintenance activities.

Generic manuals should not be substituted for the correct equipment documentation where model-specific instructions are required.
9 · Snag List

AGL Snag List and Punch List

A snag list or punch list records outstanding work, identified defects and items that require correction or verification before the relevant project stage can be closed.

Recommended snag-list fields

FieldPurpose
Item numberUnique reference
Date identifiedRecords when the issue was raised
LocationIdentifies the affected area or equipment
Equipment or circuit IDLinks the issue to the asset
DescriptionExplains the observed defect or incomplete work
PriorityIndicates the urgency under project procedures
Responsible partyIdentifies who must address the item
Corrective actionRecords the required resolution
Target dateTracks the planned completion
Verification evidenceRecords inspection, test or other proof
Closure statusOpen, in progress, awaiting verification or closed

Snag-list management process

01

Identify and document the issue.

02

Assign a unique reference and responsible party.

03

Set the priority according to the approved project process.

04

Agree on corrective action and target date.

05

Complete the corrective work.

06

Inspect or test the result as required.

07

Record the verification evidence.

08

Close the item only when the required acceptance conditions have been met.

Safety-critical deficiencies must be managed under the applicable airport procedures. They must not be treated as closed without the required corrective action and verification.
FINAL ACCEPTANCE · IS IT READY TO HAND OVER REVIEWED · WITNESSED · CLOSED · SIGNED 1 RECORDS All test results in Within the limits Nothing missing RECORD: review 2 WITNESS Key tests shown Owner watches Matches records RECORD: witnessed 3 PUNCH LIST Open items listed Each one closed Re-tested, ticked RECORD: closure 4 HANDOVER As-built drawings O&M manuals Spares & training RECORD: documents 5 SIGN-OFF Certificate drawn up Owner signs Warranty starts RECORD: certificate SYSTEM ACCEPTED OWNER SATISFIED · CERTIFICATE SIGNED 6 NOT ACCEPTED CORRECT · RE-TEST · RE-SUBMIT ACCEPTED READY FOR SERVICE SCHEMATIC · STEPS SHORTENED · NOT TO SCALE
Figure 5. Final acceptance: reviewing evidence, closing defects and handing the system over.AGL Visual Encyclopedia: What is final acceptance?
10 · Progress & Risk

AGL Project Progress Reports and Risk Registers

Progress reports help project teams compare completed work against the approved programme and identify delays, constraints and resource requirements.

Typical progress-report information

Reporting period and work locationPlanned and completed activitiesCompleted quantities and installation progressManpower and equipment deploymentMaterial delivery and approval statusInspection and test statusOutstanding defects and corrective actionsWork-front constraints and coordination issuesSafety observationsPlanned activities for the next reporting period
Progress should be reported using defined measurement rules and verified records. A percentage-complete figure should be supported by a consistent method rather than an unsupported estimate.

AGL risk register

A risk register records identified risks, their possible consequences, planned controls and assigned ownership. Typical project risk areas may include:

Delayed material approvals

Long-lead equipment procurement

Restricted airport access or work windows

Interfaces with existing electrical infrastructure

Cable route or civil-work constraints

Testing equipment or specialist personnel availability

Incomplete technical documentation

Commissioning and handover delays

Each risk should have a responsible owner, agreed control actions and a review status. The register should be updated as project conditions change.
11 · Handover

AGL Handover Documentation Checklist

The final handover package should follow the contract and airport authority requirements. The following list provides a starting point for project planning. Tick items off as you go.

Drawings & submittals

Approved drawings and final as-built records.
Final equipment and asset register.
Equipment model and serial-number schedules, where applicable.
Approved technical submittals and relevant datasheets.
0 / 4 complete

Tests & manuals

Applicable type-test and routine-test documents.
Installation inspection and commissioning reports.
Required electrical and functional test records.
Photometric reports, where specified.
Approved O&M manuals.
0 / 5 complete

Support & closure

Warranty documents.
Recommended spare-parts list.
Training and familiarisation records.
Outstanding-item and punch-list status.
Required approvals and acceptance records.
Final document register and handover transmittal.
0 / 6 complete
This checklist is not a universal contractual requirement. Confirm the actual deliverables, formats, number of copies and approval process against the project contract.
12 · Document Control

Document Control and Traceability

Document control helps ensure that all project participants use the correct information and that decisions can be traced to approved records.

Each controlled document should include the applicable identification details, such as

Document title and numberProject name or referenceRevision numberIssue dateDocument statusPrepared, checked and approved fields, where requiredApplicable drawing or specification references

Maintain a document register that records submissions, revisions, review comments, approval status and final issue details.

Superseded documents should be managed according to the project’s document-control procedure so they are not mistakenly used for current installation or maintenance activities.

ASSET DATA LIFECYCLE · MANAGING THE INFORMATION BEHIND THE ASSET CAPTURE IT · KEEP IT CURRENT · NEVER LOSE THE HISTORY 1 CREATE Asset record opened Unique ID assigned At design or purchase STEP: open 2 CAPTURE Nameplate and serial Location and circuit Install and test data STEP: collect 3 STORE Asset register Controlled access Linked to drawings STEP: hold 4 USE Plan maintenance Trace faults and spares Report condition STEP: apply 5 UPDATE After every change Repair, replace, move Checked and approved STEP: maintain 6 ARCHIVE On leaving service Retained per rules Feeds cost history STEP: retain DATA QUALITY FEEDS PLANNING: MAINTENANCE, SPARES, RENEWAL, LIFECYCLE COST INPUTS DRAWINGS · NAMEPLATES · TEST DATA · WORK RECORDS What comes from design, site and maintenance OUTPUT ASSET REGISTER · HISTORY · REPORTS Supports warranty, spares and lifecycle cost records POOR DATA: WRONG SPARES · MISSED MAINTENANCE · LOST HISTORY SCHEMATIC · SIMPLIFIED · NOT TO SCALE · STEPS OVERLAP
Figure 6. The asset data lifecycle: how information is created, captured, stored, used, updated and archived.AGL Visual Encyclopedia: What is the asset data lifecycle?
AGL Engineering Hub

Explore the AGL Engineering Knowledge Hub

Fundamentals

Standards & Compliance

Runway, Taxiway & Approach Lighting

Surface Movement & Safety

PAPI

Electrical Engineering & Power

Photometry & Testing

Maintenance, Inspection & Safety

Resources, Documentation & Careers

FAQ

Frequently Asked Questions

Q1What documents are required for AGL project handover?

The contract and airport authority determine the final list. Common deliverables include approved as-built drawings, equipment schedules, inspection and test reports, O&M manuals, warranties, spare-parts information and formal acceptance records.

Q2What is an AGL Inspection and Test Plan?

An ITP defines the inspection and testing activities, reference documents, acceptance criteria, responsible parties, inspection points and records required during project execution.

Q3What is the difference between redline and as-built drawings?

Redline drawings record changes made during construction. Final as-built drawings are the verified record of the installed configuration, prepared and approved according to the project requirements.

Q4Why is a BOQ important in an AGL project?

A BOQ identifies equipment, materials, quantities and work items. It supports procurement, cost estimation, commercial evaluation, progress measurement and contractual payment processes.

Q5What should an AGL O&M manual contain?

It should provide the system overview, equipment documentation, approved drawings, operating instructions, maintenance procedures, relevant troubleshooting guidance, safety information and applicable spare-parts details.

Q6What is the purpose of an AGL snag list?

A snag list records incomplete work and defects, assigns responsibility and tracks corrective actions through verification and closure.

Q7Are commissioning reports required for every AGL project?

The required records depend on the contract, project specifications and applicable procedures. The approved project requirements should define the inspections, tests and reports needed for acceptance.

Q8How can AGL project documentation be made more reliable?

Use controlled revisions, consistent equipment identifiers, approved templates, traceable inspection and test records, verified as-built information and a complete document register.

Q9What are airfield lighting project specifications?

Airfield lighting project specifications set the technical requirements for equipment, installation, testing and performance. They refer to standards and the approved design, and form the basis of procurement, inspection and acceptance.

Q10What are airfield lighting as-built drawings, airfield lighting as-built documentation and AGL redline drawings?

Airfield lighting as-built drawings show the installation as actually built. Redline drawings mark changes made on site against the issued drawings, and airfield lighting as-built documentation includes the final drawings, test records and schedules. Together, AGL redline drawings feed the final as-built set.

Q11What are airfield lighting handover documents?

Airfield lighting handover documents are the package given to the airport when work is complete: as-built drawings, test and commissioning reports, manuals, spares and warranty information. They enable the operator to maintain the system.

Q12What is an AGL construction sequence and AGL project execution plan?

An AGL construction sequence is the planned order of civil works, cable laying, equipment installation, testing and energisation. AGL project execution covers how the work is organised, resourced, controlled and reported. Both must allow for airside access and operational constraints.

Q13What are airfield lighting documentation requirements?

Airfield lighting documentation requirements are the documents a project must produce and keep, such as specifications, drawings, submittals, test records, manuals and as-built information. The contract and the airport's procedures define the exact list.

Q14What is airfield lighting quality assurance and an airfield lighting quality plan?

Airfield lighting quality assurance is the system that ensures work meets the specification. An airfield lighting quality plan sets out inspection points, responsibilities, test records and handling of non-conformances for a project.

Q15What is an AGL conformity assessment?

An AGL conformity assessment is the process of checking that equipment and installation conform to the applicable standards and specification, using documents, inspections and tests. The airport or regulator defines what evidence is required.

Q16What are airport lighting acceptance criteria?

Airport lighting acceptance criteria are the conditions a system must meet to be accepted: successful tests, correct operation, complete documents and closed defects. The contract and the airport's procedures define them.

Q17What is an airport lighting BOQ?

An airport lighting BOQ (bill of quantities) lists the items, quantities and units needed for the lighting works, with descriptions that match the specification. It supports pricing, procurement and progress measurement.

Q18What are airfield lighting project management and AGL project management training?

Airfield lighting project management means planning, coordinating and controlling AGL works within safety and airside constraints. AGL project management training teaches the schedule, documentation and interface skills involved; Precision AGL Academy covers these topics in its programmes.

Q19What is an airport lighting project schedule?

An airport lighting project schedule sequences design, procurement, installation, testing and handover, including airside access windows and shutdowns. It is updated with progress and reported regularly.

Q20What is an AGL risk register?

An AGL risk register lists project risks, their likelihood and effect, owners and mitigation actions. It is reviewed regularly during the project and reported with progress.

Q21What are an airfield lighting O&M manual and an AGL operation and maintenance manual?

An airfield lighting O&M manual, also called an AGL operation and maintenance manual, explains how to operate and maintain the installed system: equipment descriptions, procedures, maintenance schedules, spare parts and drawings. It is part of the handover package.

Q22What is an airfield lighting site progress report?

An airfield lighting site progress report records work done, progress against the schedule, issues, safety matters and next steps, usually with photographs and test status. It is issued at agreed intervals.

Q23What is an airport lighting punch list?

An airport lighting punch list is the list of remaining defects or incomplete items found during inspection that must be closed before final acceptance. Each item has an owner and a closure record.

Q24Is there an airfield lighting project case study?

An airfield lighting project case study reviews a real or example project, covering planning, execution, problems and lessons learned. See the Precision AGL Academy case-study resources for worked examples.

Explore More

Explore More AGL Engineering Resources

Continue learning about the engineering and delivery of airfield lighting projects. These resources complement this guide with information about design, installation, verification and practical engineering documentation.

AGL Installation and Commissioning

Installing, testing and commissioning AGL.

Open guide

AGL Testing and Inspection

Testing methods and inspection practices.

Open guide

AGL Design Engineering

Design basis, layouts and circuit planning.

Open guide

AGL Toolkit

Practical tools for AGL engineers.

Open guide
Technical disclaimer: This page provides general educational guidance. The required project documents, inspection points, acceptance criteria and handover deliverables must be confirmed against the applicable contract, approved project specifications, airport requirements and authorized procedures.
Field Insight

Engineering & Expert Notes

Write the ITP Around the Real Hold Points
ITP

An inspection and test plan is useful only if it identifies who inspects what and when. Define witness and hold points clearly.

As-Builts Must Reflect What Was Actually Built
As-Built

Collect redlines throughout construction and reconcile them before handover. Reconstructing them later introduces errors.

Control Submittals and Revisions Strictly
Document Control

Make sure approved versions are the ones used on site and that superseded documents are withdrawn.

Run Snag Lists With Owners and Dates
Snagging

Each item needs a responsible party and a closure date, otherwise the list becomes a record of open issues.

O&M Manuals Should Be Usable
Handover

Include procedures operators will actually follow, with drawings, spares lists and test records, and check them with the maintenance team.

Index the Dossier So People Can Find Things
Traceability

Use a consistent structure and naming so a future engineer can locate any record without asking the original team.

Precision AGL Academy

Understand AGL. Build Your Engineering Skills.

You now understand the documents that carry an AGL project from planning to handover, from BOQs and ITPs to as-built drawings, O&M manuals and snag lists.

Take the next step with Precision AGL Academy.

Learn AGL Step by Step

Build your knowledge through structured technical learning covering:

AGL Fundamentals Components Electrical Systems Design Photometry Testing Troubleshooting Maintenance