THE AGL ENGINEERING CENTRE by Precision AGL Academy · Practical Engineering Guide for Airfield Ground Lighting Systems

AGL Installation & Commissioning

AGL installation and commissioning is the stage where the designed airfield lighting system becomes an operational system. A component may be correctly manufactured and a design may be technically correct, but the final system can still perform incorrectly because of installation errors, incorrect connections, poor cable termination, transformer mismatch, inadequate earthing, incorrect fixture positioning, optical misalignment or incomplete testing. A proper commissioning process verifies the complete system — not simply whether the lights turn ON.

Receive → Inspect → Install → Connect → Test → Align → Energize → Measure → Commission → Handover
01 · Definitions

What Is AGL Installation & Commissioning?

AGL Installation is the physical installation and connection of airfield lighting equipment according to approved drawings, specifications and applicable standards.

AGL Commissioning is the systematic process of testing, measuring, adjusting and verifying the installed system before it is accepted for operational use.

The complete process runs from design through to handover:

01

Design

02

Installation

03

Inspection

04

Electrical Testing

05

Functional Testing

06

Alignment

07

Photometry

08

Commissioning

09

Handover

02 · Why It Matters

Why Installation Quality Matters

AGL performance depends on the relationship between equipment, location, electrical circuit, mechanical installation, optical alignment, control system, environmental protection and maintenance condition. An installation error can therefore create a system-level problem.

Installation ErrorSystem-Level Result
Incorrect transformer ratingAbnormal fixture operation
Poor connector installationIntermittent light failure
Incorrect cable terminationInsulation failure
Incorrect fixture elevationOptical performance problem
Poor foundationFixture movement
Incorrect CCR connectionCircuit malfunction
Wrong fixture orientationIncorrect visual guidance
Water ingressRepeated electrical failures
03 · Philosophy

Installation & Commissioning Philosophy

Do Not Energize First and Inspect Later.
Verify → Install → Inspect → Test → Energize → Measure → Adjust → Verify Again → Document → Handover.

The installation should progress through controlled stages, never in reverse.

04 · The Complete Chain

AGL Installation Chain

A typical installation chain runs from the approved airport layout through to final handover.

APPROVED AGL DESIGN
CIVIL / FOUNDATION WORK
CABLE INSTALLATION
TRANSFORMER & CONNECTOR INSTALLATION
LIGHT FIXTURE INSTALLATION
CCR / CONTROL INSTALLATION
MECHANICAL & ELECTRICAL INSPECTION
ELECTRICAL & FUNCTIONAL TESTING
ALIGNMENT
PHOTOMETRY
COMMISSIONING & HANDOVER

The order in which AGL works are built — set out, ground works, cables and earth, equipment, alignment, then test — with each stage checked before it is covered, because most of it ends up buried.

SECTION · WHAT GETS COVERED most of the work ends up buried HOLD POINTS · WHERE WORK STOPS each stage checked before the next COVERED AFTER CHECK 1 2 3 4 SURVEY PEG BASE CAN + DUCT CABLE IN DUCT EARTH FIXTURE 1 2 3 4 5 6 HOLDBEFORE BACKFILL HOLDBEFORE COVERING HOLDBEFORE ENERGISING A FAULT FOUND AFTER COVERING MEANS DIGGING UP SIX INSTALLATION STAGES · IN ORDER 1 SET OUTsurvey, layout fixed 2 GROUND WORKSdig, ducts, bases 3 CABLES + EARTHlay, identify, protect 4 EQUIPMENTfit, connect, seal 5 ALIGNposition, aim, torque 6 TESTprove, record
Figure 1. The order in which AGL works are built — set out, ground works, cables and earth, equipment, alignment, then test — with each stage checked before it is covered, because most of it ends up buried.
AGL Visual Encyclopedia: The installation sequence Construction sequence
05 · Before Work Starts

Pre-Installation Engineering Review

Before starting installation, verify drawings, equipment and the site.

Drawings

  • Approved AGL layout
  • Circuit drawings
  • Cable routing
  • Equipment locations
  • Foundation drawings
  • Sign locations
  • PAPI/approach lighting details
  • Control & monitoring drawings

Equipment

  • Correct equipment received
  • Correct quantities
  • Correct ratings
  • Correct specifications
  • Correct accessories
  • Manufacturer documentation available

Site

  • Work area released
  • Survey references established
  • Civil works completed
  • Cable routes available
  • Foundations ready
  • Access available
  • Work permits available
06 · Receiving Equipment

Material Receipt Inspection & Equipment Identification

Every major AGL component should be inspected before installation, and each installed component should be traceable.

ItemInspection
FixtureModel, rating, physical condition
TransformerRating, ratio, identification
ConnectorType, condition, compatibility
CableType, size, length, condition
CCRRating, configuration, condition
SignDimensions, legend, lighting condition
PAPIModel, optics, mounting accessories
Control equipmentModel and configuration
HardwareCorrect quantity and specification
Damaged or incorrect equipment should be identified before installation.

Traceability Record for Each Component

Equipment IDManufacturerModelSerial NumberRatingCircuit NumberLocationInstallation DateTest Reference

Traceability is particularly important for CCRs, isolation transformers, light fixtures, PAPI units, signs and control equipment.

07 · Civil Works

Civil & Foundation Verification

Before installing equipment, verify the civil work — and never compensate for incorrect civil work with uncontrolled equipment adjustments.

Foundation locationDimensionsElevationOrientationAnchor arrangementSurface conditionDrainageCable entryMounting interfaceFrangibility requirements

The buried concrete base that holds elevated lights, signs and PAPI units in place. It is poured by the civil team, but everything above it depends on its position and bolts.

SIDE SECTION · A FOUNDATION FOR ELEVATED EQUIPMENT GROUND LEVEL CABLE IN CONDUIT EQUIPMENT ABOVE GROUND FRANGIBLE COUPLING ANCHOR BOLTS (TEMPLATE-SET) REINFORCED CONCRETE BLOCK COMPACTED SUB-BASE CONDUIT RISES THROUGH BASE WHERE CIVIL MEETS AGL 1 POSITION & LEVEL Set from the lighting layout 2 ANCHOR BOLTS Template-set position and height 3 ORIENTATION Equipment faces the correct way 4 CONDUIT ENTRY Cable rises through the base 5 LOADS & SUB-BASE Sized for wind, mass, soil
Figure 2. The buried concrete base that holds elevated lights, signs and PAPI units in place. It is poured by the civil team, but everything above it depends on its position and bolts.
AGL Visual Encyclopedia: An AGL foundation Base-can installation
08 · Cable Work

Cable Installation & Handling

Cable Installation Checks

  • Cable type & size
  • Circuit identification
  • Routing
  • Burial depth where applicable
  • Mechanical protection
  • Bends & separation
  • Joint locations
  • Termination points
  • Cable identification

Avoid During Handling

  • Excessive pulling force
  • Sharp bends
  • Crushing & abrasion
  • Damaged insulation
  • Improper storage
  • Uncontrolled cable loops
  • Incorrect termination
Cable damage may not always be visible externally — avoid unnecessary joints in critical series circuits, and electrical testing is essential.

The excavated route that carries AGL cable across the airfield. How it is dug, bedded and backfilled decides whether the cable stays protected for decades.

CROSS-SECTION · A CABLE TRENCH DEPTH SURFACE SURFACE REINSTATEMENT COMPACTED BACKFILL WARNING TAPE PROTECTIVE COVER CABLE IN SAND BEDDING WHERE CIVIL MEETS AGL 1 ROUTE & DEPTH Set from the cable-route design 2 BEDDING Clean material around the cable 3 COVER & TAPE Protection and warning above 4 CROSSINGS Pavement, drains, other services 5 REINSTATEMENT Compacted backfill and surface
Figure 3. The excavated route that carries AGL cable across the airfield. How it is dug, bedded and backfilled decides whether the cable stays protected for decades.
AGL Visual Encyclopedia: A cable trench Cable installation
09 · Series Circuit

Series Circuit & Isolation Transformer Installation

A typical series circuit follows a defined sequence — the actual arrangement depends on the project.

CCR
Primary Cable
Isolation Transformer
Connector
Light Fixture
Return to CCR

During installation, verify circuit sequence, transformer connection, cable continuity, connector compatibility, circuit identification, circuit separation and correct termination. Before installing the transformer itself, also check its rating, primary and secondary connectors, physical condition, identification, insulation condition, installation location, water protection and cable compatibility.

Isolation Transformer Installation — Cross-Section

The primary series cable loops through the pit to the next fixture; the transformer's secondary feeds only the local fixture — verify sealing, drainage and connector orientation at every pit

Pavement / ground level ELEVATED FIXTURE Frangible coupling Primary series cable — loops through, pit to pit LIGHT BASE / PIT ISOLATION TRANSFORMER Primary in Primary out Secondary connector kit Drainage / weep provision Verify at every pit: seal, drainage, connector orientation, correct loop-through, and fixture bond
10 · Connectors & Fixtures

Connector & Fixture Installation

Primary & Secondary Connectors

  • Correct connector type & cable
  • Correct termination & mating
  • Correct polarity where applicable
  • Contact condition & mechanical locking
  • Insulation & waterproofing
  • Strain relief & identification

A poor connector can create high-resistance connections, intermittent faults or complete circuit failure — never assume a connector is correctly installed simply because it fits.

Light Fixtures — Inset & Elevated

  • Correct type, location & orientation
  • Correct elevation & mounting
  • Correct frangibility arrangement
  • Correct transformer connection
  • Correct optical direction
  • Drainage, sealing & cable routing

Fixture installation should be based strictly on the approved layout — never on assumed positions.

Fitting the light to its base can or mounting — a clean, drained base, a new seal, the secondary connector made and sealed, the fixture seated at the design level and bolted to the specified torque, then tested before the area is handed back.

INSET FIXTURE · SECTIONbase can, seal, bolts, sealed lead ELEVATED FIXTURE · ELEVATIONfrangible coupling, design height PAVEMENT BOLTS FIXTURE GASKET / O-RING SEC. CONNECTOR SLACK LEAD DRAINED BASE GROUND BASE CAN DESIGNHEIGHT FIXTURE HEAD MAST FRANGIBLE COUPLING BREAK POINT SIX INSTALLATION CHECKS · IN ORDER 1 ISOLATElock out, prove dead 2 PREPAREclean base, new seal 3 CONNECTsealed, with slack 4 SEATlevel, at design height 5 TORQUEcalibrated, as specified 6 TESTlight, record, no FOD
Figure 4. Fitting the light to its base can or mounting — a clean, drained base, a new seal, the secondary connector made and sealed, the fixture seated at the design level and bolted to the specified torque, then tested before the area is handed back.
AGL Visual Encyclopedia: Fixture installation Connector installation
11 · By Lighting System

Installation by Lighting System

Runway Lighting

Edge, centreline, threshold, end, touchdown zone and approach lights — checked for location, spacing, orientation, elevation, colour, circuit assignment and electrical connection.

Taxiway Lighting

Edge, centreline, stop bars, runway guard lights, lead-on/lead-off and intersection lighting — installed to the approved layout and applicable standards.

Approach Lighting

Positions, centreline reference, crossbar arrangement, structural supports, elevation, alignment, frangibility, cable routing and sequencing — geometry and alignment are critical here.

PAPI

Location, elevation, unit spacing, foundation, mounting, frangibility, electrical supply, optical aiming and alignment. PAPI is not commissioned simply because all units illuminate.

Airfield Signs

Identification, location, orientation, height, mounting, foundation, frangibility, electrical supply, illumination, legend visibility and brightness — matched exactly to the approved sign schedule.

CCR

Rating, input supply, output current, number of steps, circuit assignment, control interface, monitoring, protection, earthing, panel condition and alarm/fault indication.

Putting each light of the approach line into service — set out from survey on the extended runway centreline, fixed on a flush foundation through a frangible stem or mast, connected to its transformer and cable, then aimed and proved.

PLAN VIEW · APPROACH LINE positions on the extended centreline ELEVATION · ONE POSITION foundation, frangible stem, fixture, aim THRESHOLD RUNWAY SPACING AS DESIGNED EACH POSITION SET OUT FROM SURVEY CROSSBAR APPROACH DIRECTION GROUND DESIGN PLANE AIMING ANGLE AS DESIGNED HEIGHT TO DESIGN PLANE TRANSFORMER CAN CABLE IN EARTH FIXTURE STEM OR MAST FRANGIBLE COUPLING BREAK POINT FOUNDATION SIX APPROACH-LIGHT INSTALLATION STEPS · IN ORDER 1 ISOLATElock out, prove dead 2 SET OUTsurvey, line, spacing 3 MOUNTfrangible, plumb, height 4 CONNECTcable, earth, seal 5 AIMfixture, design angle 6 TESTprove, record
Figure 5. Putting each light of the approach line into service — set out from survey on the extended runway centreline, fixed on a flush foundation through a frangible stem or mast, connected to its transformer and cable, then aimed and proved.
AGL Visual Encyclopedia: Approach-light installation PAPI installation
Medium-intensity approach lighting system with runway alignment indicator lights, shown on an FAA page
Photo 1. A medium-intensity approach lighting system (MALSR) as published by the FAA: white light bars and flashers on the extended centreline, with a green threshold line.Credit: Federal Aviation Administration. US Government work, public domain. Source page
12 · Control & Earthing

CCR Connection, Control & Earthing

Incorrect CCR wiring can affect the complete lighting circuit — verify the full chain and every control function.

Incoming Supply
Protection
CCR
Series Circuit
Transformers
Fixtures

Control & Monitoring

  • Local & remote control
  • Intensity selection
  • Circuit ON/OFF
  • Fault indication & monitoring
  • Communication & interlocks
  • Emergency functions

Earthing & Bonding

  • CCR & control panels
  • Equipment enclosures
  • Metal structures & signs
  • PAPI equipment
  • Cable protection systems
  • Other applicable equipment
Earthing & Bonding Network

Every enclosure, structure and metallic casing bonds back to a common earth reference — a missing or high-resistance bond is a safety and fault-detection risk, not just a paperwork item

CCR / CONTROL PANEL TRANSFORMER CASING METAL STRUCTURE AIRFIELD SIGN PAPI EQUIPMENT COMMON EARTH REFERENCE / EARTH GRID Earth electrode / rod

Putting in the earth that waits for the day something fails — a conductor laid with the cable, rods and pits, sound joints, equipment bonded to it, and the resistance measured and recorded.

TRENCH · SECTION earthing conductor laid with the cable EARTH ROD & BOND · ELEVATION pit, test link, joints and bond lead GROUND LEVEL COVER AS DESIGNED EARTHING CONDUCTOR SERIES CIRCUIT CABLE WARNING TAPE COMPACTED BACKFILL · NO SHARP STONES GROUND EARTHING CONDUCTOR TEST LINK EARTH PIT WELDED JOINT GROUND ROD BOND LEAD FIXTURE BASE CAN SIX EARTHING INSTALLATION STEPS · IN ORDER 1 ISOLATElock out, prove dead 2 LAYconductor with the cable 3 DRIVErods and earth pits 4 JOINsound, protected joints 5 BONDequipment metalwork 6 MEASUREresistance, record
Figure 6. Putting in the earth that waits for the day something fails — a conductor laid with the cable, rods and pits, sound joints, equipment bonded to it, and the resistance measured and recorded.
AGL Visual Encyclopedia: Earthing installation
13 · Before Power On

Pre-Energization Inspection

Before applying power, perform a complete inspection. No unresolved critical defect should remain before energization.

Correct equipmentCorrect circuitCorrect connectionsCorrect transformerCorrect connectorsCable termination completeEarthing completeNo exposed conductorsNo loose connectionsEquipment covers installedControl wiring completeCircuit identification completeWork area clear

The static, de-energised checks made on a finished installation — proving the system is built, connected and recorded correctly before power is ever applied.

PRE-COMMISSIONING · STATIC CHECKS BEFORE POWER DE-ENERGISED · CCR LOCKED OUT · NO LIVE TESTS 1 DOCUMENTS As-built drawings Circuit schedules Permit & test plan RECORD: documents 2 INSTALLATION Fixtures aligned Torque & seating Labels & cleanliness RECORD: inspection 3 CABLES Loop continuity Insulation resistance Joints & connectors RECORD: cable log 4 EARTHING Earth resistance Bonding continuity Earth pits RECORD: earth log 5 EQUIPMENT CCR & controls Transformers & lamps Settings recorded RECORD: settings HOLD POINT READINESS SIGN-OFF · RECORDS REVIEWED 6 OPEN ITEM RECTIFY · RE-TEST CLEARED READY FOR ENERGIZATION SCHEMATIC · CHECK LISTS SHORTENED · NOT TO SCALE
Figure 7. The static, de-energised checks made on a finished installation — proving the system is built, connected and recorded correctly before power is ever applied.
AGL Visual Encyclopedia: Pre-commissioning
14 · Electrical Testing

Electrical Testing

The exact test values and methods must follow the applicable equipment standard, manufacturer requirements and project specification.

Cable

  • Continuity
  • Insulation resistance
  • Conductor integrity
  • Circuit identification

Transformers

  • Continuity & insulation
  • Ratio/functional verification where applicable
  • Physical inspection

CCR

  • Input supply
  • Output current
  • Step operation
  • Protection, control & monitoring

Earthing

  • Ground continuity
  • Earth resistance where applicable
  • Bonding verification

Insulation Resistance Testing Helps Identify

Cable insulation deteriorationMoistureDamaged cableIncorrect terminationConnector problemsGround leakage

Always isolate sensitive electronic equipment before applying insulation-test voltage where required by the manufacturer.

Insulation Resistance Test — Circuit to Earth

One test lead on the isolated circuit conductor, one on earth — a low reading anywhere on the loop means moisture, damage or a failed connector somewhere between the CCR and the last fixture

MEGOHMMETER Isolated circuit Circuit conductor XFMR XFMR XFMR Moisture ingress Cable damage Failed connector Loop continues to last fixture Earth reference

Continuity Test Sequence

CCR
Cable
Transformer
Connector
Fixture
Return Circuit
15 · Controlled Power-Up

First Energization

The first energization should always be controlled — never sudden, and never unattended.

1

Final Inspection

2

Confirm Personnel Clear

3

Confirm Circuit Identification

4

Confirm Protection

5

Energize at Minimum/Initial Operating Condition

6

Observe Current, Fixtures, Noise & Heating

7

Check Fault Indications

8

Increase Operating Level As Required

9

Record Results

16 · Functional & Visual

Functional Testing & Visual Inspection After Energization

Functional Testing

  • ON/OFF & intensity steps
  • Control & remote operation
  • Monitoring & fault indication
  • Interlocks
  • Automatic functions where applicable

Every intended operating mode should be tested.

Visual Inspection

  • Flickering & uneven intensity
  • Dark fixtures & abnormal colour
  • Excessive brightness variation
  • Transformer noise & heating
  • Connector, cable & control faults

Do not rely only on the control panel indication — inspect the actual airfield lighting.

Operating checks on the live system — proving every circuit, brightness step and control does what the design requires, not just that it powers up.

FUNCTIONAL TESTING · DOES IT DO ITS JOB LIVE SYSTEM · OPERATED AS A USER WOULD 1 CIRCUITS Each circuit selected Right fixtures lit Colour & direction RECORD: lit check 2 BRIGHTNESS Every step selected Lamps respond evenly Current matches step RECORD: steps 3 CONTROLS Local control Remote control Selector & interlocks RECORD: controls 4 MONITORING Status indications Alarm responses Fail-safe behaviour RECORD: alarms 5 SEQUENCES Flashing & sequence Stop-bar selection Where fitted RECORD: modes FUNCTION VERIFIED EVERY CIRCUIT · EVERY MODE 6 DEFECT ISOLATE · FIX · RE-TEST PASSED READY FOR INTEGRATION SCHEMATIC · CHECKS SHORTENED · NOT TO SCALE
Figure 8. Operating checks on the live system — proving every circuit, brightness step and control does what the design requires, not just that it powers up.
AGL Visual Encyclopedia: Functional testing
17 · Optical Performance

Alignment & Photometric Verification

Alignment answers: is it pointing correctly?
Photometry answers: is it performing correctly?

Lighting systems requiring directional accuracy — PAPI, approach lights, runway centreline lights, directional inset fixtures and other precision visual aids — should be aligned using appropriate engineering references:

Reference
Measure
Adjust
Lock
Re-Measure
Record

Photometry is particularly important after a new installation, fixture replacement, major maintenance, alignment adjustment or system modification, and may measure intensity, distribution, colour, beam alignment, uniformity, fixture performance and system performance.

Explore AGL Photometry

Checking the 4Cs, Colour, Candela, Coverage and Configuration, then accepting or rejecting the fixture.

THE 4Cs · ACCEPTANCE DECISIONCOLOURChromaticityCANDELAIntensityCOVERAGEBeam spread and aimCONFIGURATIONPlacement and layoutALL FOURMEET?YESNOACCEPTREJECTINVESTIGATERETEST123451COLOURChromaticity within its region2CANDELAIntensity meets the requirement3COVERAGEBeam spread and aim are correct4CONFIGURATIONPlacement, spacing, layout5DECISIONEvery C must pass to acceptSCHEMATIC · THE ACTUAL CRITERIA COME FROM THE STANDARD AND THE PROCEDURE
Figure 9. Checking the 4Cs, Colour, Candela, Coverage and Configuration, then accepting or rejecting the fixture.
AGL Visual Encyclopedia: Photometric acceptance decided Fixture alignment
18 · System-Level Verification

Commissioning by System

A successful commissioning result means the system performs as an integrated system, not merely that individual components pass tests.

POWER
CONTROL
CIRCUIT
EQUIPMENT
OPTICAL OUTPUT
OPERATIONAL FUNCTION

Runway Lighting

Edge, centreline, threshold, end, TDZ where applicable, intensity, colour and circuit operation.

Taxiway Lighting

Edge, centreline, stop bars, runway guard lights, lead-on/lead-off, control and intensity.

Approach Lighting

Light positions, alignment, sequencing, intensity, control and structural installation.

PAPI

Location, elevation, alignment, optical performance, control and electrical performance.

Signs

Legend, location, orientation, illumination, control and photometric performance.

Five Commissioning Questions

Installed correctly? Electrically healthy? Operates correctly? Produces required visual performance? Ready for operation?

Siting, aiming and proving the approach path indicator — so the red and white signal a pilot sees marks the correct glide path.

PAPI COMMISSIONING · IS THE GLIDE PATH RIGHT SITED · AIMED · PROVED BEFORE PILOTS RELY ON IT 1 SITING Position vs design Offset from runway Units in line RECORD: position 2 LEVEL & AIM Units firm, levelled Angle set per unit Calibrated instrument RECORD: angles 3 ELECTRICAL Circuit energised Brightness steps Units match in output RECORD: circuit 4 SIGNAL CHECK Red & white seen From approach path Obstacles cleared RECORD: signal 5 FLIGHT CHECK Flight inspection Glide path confirmed Transition as designed RECORD: flight PAPI COMMISSIONED EVERY UNIT · RIGHT ANGLE 6 DEFECT RE-AIM · FIX · RE-TEST PASSED READY FOR ACCEPTANCE SCHEMATIC · CHECKS SHORTENED · NOT TO SCALE
Figure 10. Siting, aiming and proving the approach path indicator — so the red and white signal a pilot sees marks the correct glide path.
AGL Visual Encyclopedia: PAPI commissioning
PAPI light boxes beside a runway at Washington Dulles, showing a red and white pattern
Photo 2. A PAPI installation at Washington Dulles, from the FAA. Siting and aiming decide which red and white pattern the pilot sees.Credit: Federal Aviation Administration. US Government work, public domain. Source page
19 · Interactive · Troubleshooting

Common Commissioning Failures

This is where installation and commissioning connect directly with the AGL Troubleshooting Atlas. Tap a symptom to see possible causes.

Lights Operate but Photometry Fails

Possible Causes

  • Optical contamination
  • Incorrect alignment
  • Incorrect fixture
  • LED/lamp degradation
  • Incorrect intensity
  • Installation geometry problem

CCR Current Is Abnormal

Possible Causes

  • Circuit fault
  • Incorrect transformer
  • Cable problem
  • Excessive load
  • Short circuit

One Fixture Remains Dark

Possible Causes

  • Connector
  • Transformer
  • Fixture
  • Cable
  • Internal component

Multiple Fixtures Fail

Investigate Common Circuit Elements First

  • CCR
  • Feeder
  • Cable
  • Transformers
  • Control

PAPI Indication Is Abnormal

Possible Causes

  • Unit alignment
  • Elevation
  • Optical condition
  • Electrical supply
  • Geometry

Common Installation Defects

Frequent Root Causes

  • Incorrect transformer rating
  • Poor connector termination
  • Damaged cable / poor earthing
  • Incorrect elevation or PAPI alignment
  • Wrong sign legend / poor sealing
20 · Quality Control

Installation QA/QC — Three Levels & Hold Points

A strong installation QA/QC process should have three levels, preventing defects from being discovered only at final commissioning.

LEVEL 1

Incoming Inspection

Verify equipment before installation.

LEVEL 2

Installation Inspection

Verify the physical installation.

LEVEL 3

Commissioning Inspection

Verify electrical, functional and optical performance.

Recommended Installation Inspection Hold Points

HP-01

Material approval

HP-02

Foundation inspection

HP-03

Cable installation

HP-04

Transformer installation

HP-05

Connector termination

HP-06

Fixture installation

HP-07

CCR/control connection

HP-08

Pre-energization inspection

HP-09

Electrical testing

HP-10

First energization

HP-11

Photometry/alignment

HP-12

Final commissioning

Planned checks made at each stage of an AGL installation — base can, cable, connectors, fixture and earthing — so faults are found before the work is buried and the circuit is signed off before it is energised.

THE INSTALLATION · SECTION five things checked before they are buried THE RECORD · SIGN-OFF checked, tested, signed, then energised PAVEMENT DRAIN CABLE IN DUCT EARTH 1 2 3 4 5 INSPECTION RECORD BASE CAN CABLE AND DUCT CONNECTORS FIXTURE EARTHING AND BONDING 6 TEST SIGN OFF ENERGISE 1BASE CANposition, level, grouted, drained 2CABLE AND DUCTrouted, protected, identified, entry sealed 3CONNECTORSmade correctly, sealed, tested 4FIXTUREaligned, at elevation, torqued 5EARTHING AND BONDINGjoints sound, continuity proved 6RECORDED AND SIGNEDresults and as-builts kept CORRECT PRACTICECHECKED AT EVERY STAGE, THEN SIGNED OFFFaults found while they are still cheap to fix WRONG PRACTICECHECKED ONLY AT THE END, IF AT ALLBuried faults, rework and an unreliable circuit SCHEMATIC · NOT TO SCALE · FOLLOW THE PROJECT SPECIFICATION
Figure 11. Planned checks made at each stage of an AGL installation — base can, cable, connectors, fixture and earthing — so faults are found before the work is buried and the circuit is signed off before it is energised.
AGL Visual Encyclopedia: Installation quality checkpoints
21 · Documentation

Commissioning Package, Report & Punch-List Management

Commissioning Package Contents

  • Approved drawings & equipment schedule
  • Material & installation inspection records
  • Cable, insulation & continuity test reports
  • Transformer, CCR & earthing test records
  • Functional & alignment records
  • Photometry reports
  • Punch-list & final commissioning report
  • As-built drawings

Punch-List Entry Fields

  • Defect number & location
  • Affected equipment & description
  • Severity — Critical/Major/Minor
  • Corrective action & responsible party
  • Target date & status
  • Verification — re-test result

Re-Testing After Rectification

A defect is not closed simply because corrective work is completed: Defect → Rectification → Inspection → Re-test → Result → Close. A repaired cable repeats the electrical test; a replaced connector repeats continuity/insulation checks; a replaced fixture repeats functional and optical verification; an adjusted PAPI repeats alignment/photometry; a corrected CCR fault repeats operational testing.

Never hand over drawings that represent the design but not the actual installation — as-built documentation must reflect the actual installed system.

The drawings and tables that show what was actually installed, circuit by circuit — checked against the site, kept current, and used for every later test and repair.

AS-BUILT RECORDS AND CIRCUIT SCHEDULES · WHAT WAS ACTUALLY INSTALLED RECORD AS BUILT · SAME REFERENCES · KEEP CURRENT 1 MARK UP Red-line site changes Routes and positions Note every deviation STEP: record 2 VERIFY Survey routes and pits Match tags to drawing Confirm equipment STEP: check 3 REDRAW Update the drawings Same circuit references New revision issued STEP: issue 4 SCHEDULE List each circuit Cable, lights, load Add test values STEP: tabulate 5 APPROVE Compare with the site Check against design Sign and date STEP: confirm 6 HAND OVER Into asset register Linked to each asset Controlled copies out STEP: file EVERY REPAIR, RE-ROUTE OR UPGRADE LOOPS BACK: THE RECORDS ARE UPDATED, NOT LEFT BEHIND INPUTS RED-LINES · SURVEY · TESTS · EQUIPMENT DATA What the records are built from OUTPUT AS-BUILT SET · CIRCUIT SCHEDULES Baseline for tracing, testing and maintenance POOR RECORDS: WRONG CABLE TRACED · WRONG LOAD ASSUMED · SLOW FAULT FINDING SCHEMATIC · SIMPLIFIED · NOT TO SCALE · STEPS OVERLAP
Figure 12. The drawings and tables that show what was actually installed, circuit by circuit — checked against the site, kept current, and used for every later test and repair.
AGL Visual Encyclopedia: As-built records and circuit schedules
Keyword Reference

Airport Lighting Installation: Overview, Procedure & Method Statement

How an airfield lighting installation is planned, sequenced and documented before work starts on site.

Airport lighting installation

Airport lighting installation is the physical work of placing, connecting and securing airfield lighting equipment to the approved design. It covers civil preparation, cable and duct work, transformers, connectors, fixtures, CCR connection and earthing. Done well, it is the foundation for a commissioning that passes first time.

Airfield lighting installation overview

At overview level, installation follows a chain: engineering review, material receipt, civil and foundation verification, cable installation, transformer and connector installation, fixture installation and CCR connection. Each step has its own checks and hold points before the next one starts. See the AGL Installation Chain and Pre-Installation Engineering Review sections above.

AGL installation procedure

An AGL installation procedure sets out the order of work, who does it, the checks at each stage and the records to be kept. A typical procedure covers setting out, base and foundation work, cable laying, termination, fixture mounting, alignment and pre-energization inspection. It should follow the manufacturer's instructions and the project specification.

Airport lighting installation method statement

A method statement describes how a specific piece of airfield lighting work will be carried out safely and correctly. It normally covers scope, resources, sequence, equipment, quality checks, airside safety, permits, working-hours restrictions and coordination with airport operations. It is usually approved before work begins.

AGL method statement

An AGL method statement is the working document the site team follows. It should be specific to the system involved, such as edge lights, centreline lights or approach lights, and should state the hold points where inspection is required before work continues.

Keyword Reference

Elevated Lights, Base Cans, Shallow Bases & Foundation Details

Mounting arrangements and the civil work that supports the fixture.

Elevated light installation

Elevated light installation covers lights mounted above the surface on frangible supports, such as many edge and approach lights. Key points are correct height and orientation, frangible coupling arrangements, secure foundation, correct connector mating and protection of leads. Always check against the project drawings and the standard being followed.

Airfield lighting base can installation

Base can installation provides the housing in which an in-pavement fixture and its transformer sit. The base must be positioned and levelled to the design, drained and sealed as specified, and protected during paving and construction. Errors in position or level are difficult and costly to correct later.

AGL shallow base installation

Shallow base installation is used where depth is limited, for example in thin pavement or overlay situations. It needs the same attention to position, level, sealing and cable entry as a conventional base can, with extra care over fixture fit and drainage. Follow the manufacturer's instructions for the specific base type.

Airport lighting foundation details

Foundation details show how each fixture, base or support is anchored, including dimensions, materials and the cable and duct entry arrangements. They come from the civil and electrical drawings, and the installer should verify the foundation matches them before fitting equipment. See Civil & Foundation Verification above.

Keyword Reference

AGL Installation Testing, Defects & Pre-Commissioning

Proving the installation is sound before the circuit is energised.

AGL installation testing

Installation testing proves the work is electrically and mechanically sound before commissioning. It normally includes cable and insulation resistance testing, continuity checks, connector inspection and earthing checks, with results recorded against the project's acceptance criteria. Figures come from the project specification, so none are given here. See the Electrical Testing section above.

AGL installation defects

Typical installation defects include poorly made connectors, water ingress, damaged cable insulation, wrong fixture orientation, incorrect transformer rating, poor earthing and base level errors. Defects should be logged, assigned and closed with evidence, and repeat defects fed back into the method statement.

Airfield lighting pre-commissioning

Pre-commissioning is the set of checks done before first energization: verifying the installation matches drawings, completing insulation and continuity tests, confirming labelling and checking that protection and control settings are correct. It reduces the chance of a fault appearing during energization. See Pre-Energization Inspection above.

Keyword Reference

Airfield Lighting Commissioning: Procedure, SAT Testing, Report & Dossier

Bringing the system into service and documenting that it meets requirements.

Airfield lighting commissioning

Airfield lighting commissioning proves that the installed system works as designed and is ready for operational use. It covers energization, functional testing, brightness step checks, control and monitoring checks, alignment and photometric verification, followed by documented acceptance.

Airfield ground lighting commissioning

Airfield ground lighting commissioning is commissioning of the full AGL system, including circuits, CCRs, fixtures and control. It is carried out system by system, such as runway, taxiway and approach lighting, and ends with a commissioning package and handover. See Commissioning by System above.

AGL commissioning procedure

An AGL commissioning procedure defines the order of tests, the conditions for each, acceptance criteria, safety rules and the people who witness or sign off. It is normally agreed with the airport operator before testing begins.

Airport lighting SAT testing

SAT, or site acceptance testing, is the formal demonstration on site that the installed system meets the contract and design requirements. It is witnessed by the client or their representative, and results are recorded and signed off. Test content and acceptance values come from the project specification.

Airfield lighting commissioning report

The commissioning report records what was tested, the results, any deviations and their closure, and the final status of the system. It should be traceable to circuits, equipment and test records, and signed by the responsible parties. See Commissioning Package, Report & Punch-List Management above.

AGL commissioning report template

A commissioning report template gives each project a consistent layout: project and system identification, equipment list, test results, punch list, deviations, photographs and sign-off blocks. Adapt the template to your project specification and the client's required format.

AGL commissioning dossier

The commissioning dossier is the complete handover file. It typically gathers as-built drawings, test records, calibration certificates, commissioning reports, punch-list closure, manuals and warranties, so the operator has a full record of the system as delivered.

The planned order for bringing an AGL system into service — each stage passed and recorded before the next begins.

COMMISSIONING SEQUENCE · IN WHAT ORDER PASS · RECORD · HOLD · THEN THE NEXT STAGE 1 PRE-COMMISSION Installation checked Circuit tests done Records ready HOLD: ready to energize 2 ENERGIZATION Controlled switch-on Steps raised in turn Readings watched HOLD: stable on all steps 3 FUNCTIONAL Each light and control Steps and alarms Local and remote HOLD: works as designed 4 INTEGRATION Circuits run together Interlocks proven Fault behaviour HOLD: system agrees 5 ALCMS LINK Control signals Status feedback Failure handling HOLD: command = response 6 PAPI Aiming and settings Glide path angle Flight check if required HOLD: angles confirmed 7 SIGNS Legends correct Brightness steps Control and status HOLD: signs correct 8 ACCEPTANCE Records reviewed Key tests witnessed Certificate signed HOLD: owner accepts A STAGE FAILS CORRECT · RE-TEST · REPEAT ALL EIGHT PASSED READY FOR SERVICE SCHEMATIC · STEPS SHORTENED · NOT TO SCALE
Figure 13. The planned order for bringing an AGL system into service — each stage passed and recorded before the next begins.
AGL Visual Encyclopedia: The commissioning sequence Final acceptance
22 · Interactive Checklist

AGL Installation & Commissioning Checklist

A complete project should be checked across four stages. Tick items off as you review a project — this resets on reload.

Pre-Installation

Approved drawings available
Equipment approved & materials inspected
Site released
Survey references established
0 / 4 complete

Installation

Foundations verified & cables installed
Transformers & connectors installed
Fixtures, CCR & control installed
Earthing completed
0 / 4 complete

Testing & Energization

Circuit ID, continuity & insulation tested
Connections inspected & earthing verified
Controlled energization completed
Functional testing complete
0 / 4 complete

Handover

Alignment & photometry complete
Defects closed & documentation complete
As-built drawings complete
Client acceptance completed
0 / 4 complete
23 · Installation vs Commissioning

Installation vs Commissioning

InstallationCommissioning
Physical workVerification work
Equipment placementEquipment performance
Cable installationCable testing
Transformer installationTransformer verification
Fixture installationOptical verification
CCR connectionCCR functional testing
Connector terminationElectrical testing
Mechanical assemblyAlignment
ConstructionAcceptance

Installation creates the system.
Commissioning proves the system.

24 · Standards & References

Standards & References

Installation and commissioning should be performed against the current applicable edition of the relevant standards, project specifications and manufacturer instructions. Exact acceptance criteria should always be taken from the applicable standard, approved design and project specification — never one universal value applied to every installation.

ICAO Annex 14ICAO aerodrome design guidanceFAA AC 150/5340 seriesApplicable FAA equipment specificationsFAA maintenance guidanceApplicable IEC standardsApplicable Indian StandardsDGCA requirementsAirport-specific technical specificationsApproved project drawingsManufacturer installation manualsApproved inspection & test plans
Test Yourself

Quick Knowledge Check

Q1. What is the basic principle of AGL commissioning philosophy?

A. Energize first, inspect later
B. Skip inspection if the schedule is tight
C. Verify, install and inspect before energizing
D. Only test after client complaints

Q2. A defect is closed once corrective work is completed. True or false?

A. True — completion of repair closes the defect
B. False — it must be re-tested and verified before closing

Q3. Lights turn ON during first energization. Is the system commissioned?

A. Yes, ON is sufficient
B. Yes, if the CCR shows no fault
C. Only if the client is present
D. No — installation, electrical, mechanical, functional, optical and documentation requirements must all be verified
The Final Engineering Principle

AGL installation is not simply placing lights on the airfield. Commissioning is not simply switching them ON.

Install Correctly → Connect Correctly → Test Electrically → Verify Mechanically → Align Optically → Measure Photometrically → Operate Functionally → Document Completely.

Go Deeper

AGL Installation & Commissioning Knowledge Hub

Installation Fundamentals

Understand the complete installation process.

Start here →

AGL Cable Installation

Study cable routing, handling and termination.

Review section →

Transformer Installation

Understand isolation transformer installation and testing.

Browse components →

CCR Installation & Testing

Study CCR installation, connection and functional testing.

Open Design & Electrical Engineering →

AGL Electrical Testing

Insulation, continuity, circuit and equipment testing.

Review section →

AGL Photometry

Measure actual optical performance.

Open AGL Photometry →

AGL Inspection Checklists

Use structured field inspection procedures.

Review checklist →

AGL Standards Library

Explore applicable standards and requirements.

Open standards →

From Delivered Equipment to a Verified System

Available for AGL installation supervision, commissioning support and technical documentation across Indian airports.

AGL Engineering Hub

Explore the AGL Engineering Knowledge Hub

Fundamentals

Standards & Compliance

Runway, Taxiway & Approach Lighting

Surface Movement & Safety

PAPI

Electrical Engineering & Power

Photometry & Testing

Maintenance, Inspection & Safety

Resources, Documentation & Careers

FAQ

Frequently Asked Questions

Q1What is AGL installation and commissioning?

AGL installation is the physical installation and connection of airfield lighting equipment according to approved drawings, specifications and applicable standards. AGL commissioning is the systematic process of testing, measuring, adjusting and verifying the installed system before it is accepted for operational use. Commissioning verifies the complete system, not simply whether the lights turn on.

Q2Why does installation quality matter so much in AGL?

An installation error can create a system-level problem. For example, an incorrect transformer rating can cause abnormal fixture operation, a poor connector installation can cause intermittent light failure, incorrect cable termination can lead to insulation failure, incorrect fixture elevation can cause an optical performance problem, and water ingress can cause repeated electrical failures.

Q3What is the AGL installation and commissioning philosophy?

Do not energize first and inspect later. The installation should progress through controlled stages, never in reverse: verify, install, inspect, test, energize, measure, adjust, verify again, document and hand over.

Q4What are the stages from design to handover?

The process runs through design, installation, inspection, electrical testing, functional testing, alignment, photometry, commissioning and handover.

Q5What should be checked before AGL installation starts?

A pre-installation review covers drawings (approved layout, circuit drawings, cable routing, equipment locations, foundation drawings), equipment (correct items, quantities, ratings, specifications and manufacturer documentation) and the site (work area released, survey references, civil works completed, cable routes, foundations, access and work permits).

Q6Why is equipment traceability important?

Every major AGL component should be inspected on receipt and traceable afterwards. A traceability record can include equipment ID, manufacturer, model, serial number, rating, circuit number, location, installation date and test reference. It is particularly important for CCRs, isolation transformers, light fixtures, PAPI units, signs and control equipment.

Q7Why must civil and foundation work be verified first?

Foundation location, dimensions, elevation, orientation, anchors, drainage, cable entry, mounting interface and frangibility requirements must be verified before equipment is installed. Incorrect civil work should never be compensated for with uncontrolled equipment adjustments.

Q8How can cable damage be avoided during installation?

Avoid excessive pulling force, sharp bends, crushing and abrasion, damaged insulation, improper storage, uncontrolled cable loops and incorrect termination. Cable damage may not be visible externally, so electrical testing is essential, and unnecessary joints should be avoided in critical series circuits.

Q9What is verified when installing the series circuit and isolation transformers?

Verify the circuit sequence, transformer connection, cable continuity, connector compatibility, circuit identification, circuit separation and correct termination. Before installing a transformer, also check its rating, primary and secondary connectors, physical condition, identification, insulation condition, location, water protection and cable compatibility.

Q10How should light fixtures and connectors be installed?

Fixture installation should follow the approved layout strictly, never assumed positions, with correct type, location, orientation, elevation, frangibility arrangement, transformer connection and optical direction. A connector should never be assumed correctly installed simply because it fits, since a poor connector can cause high-resistance connections, intermittent faults or complete circuit failure.

Q11How to commission an AGL system?

Commissioning an AGL system follows a set order: complete installation and pre-commissioning checks, run insulation and continuity tests, carry out a pre-energization inspection, energize each circuit under controlled conditions, then do functional testing at each brightness step. Next check control and monitoring, alignment and photometry, and close out the punch list. The results go into the commissioning report and dossier, and acceptance values come from your project specification.

Field Insight

Engineering & Expert Notes

Check Before You Cover
Hold Points

Define hold points for work that will be buried or concealed. Verification afterwards is expensive and sometimes impossible.

Inspect Materials on Receipt
Receipt

Check type, rating, markings and condition against the approved submittal when equipment arrives, and quarantine anything that does not match.

Verify Civil Work Before the Electrical Work Depends on It
Foundations

Levels, positions and drainage set by civil teams determine installation quality. Confirm them against the drawings before fixtures are fitted.

Test in Stages, Not Only at the End
Testing

Cable, transformer and circuit tests at each stage isolate problems when they are cheap to fix. Record results as you go.

Electrical Pass Does Not Mean Photometric Pass
Verification

A circuit can be healthy electrically while optical output or alignment is wrong. Include optical verification in the commissioning scope.

Build the Handover File as the Work Proceeds
Handover

Collecting records at the end invites gaps. Compile test sheets, as-builts and certificates progressively and review them before completion.

Precision AGL Academy

Understand AGL. Build Your Engineering Skills.

You now understand how AGL systems are installed and commissioned on site — from cable laying and terminations to testing, snagging and final handover.

Take the next step with Precision AGL Academy.

Learn AGL Step by Step

Build your knowledge through structured technical learning covering:

AGL Fundamentals Components Electrical Systems Design Photometry Testing Troubleshooting Maintenance

Move from understanding how AGL works to developing the practical knowledge needed to analyse, operate and maintain complete AGL systems.

Understand the system. Build the knowledge. Apply the engineering.