What is functional testing?

Operating checks on the live system — proving every circuit, brightness step and control does what the design requires, not just that it powers up.

FUNCTIONAL TESTING · DOES IT DO ITS JOB LIVE SYSTEM · OPERATED AS A USER WOULD 1 CIRCUITS Each circuit selected Right fixtures lit Colour & direction RECORD: lit check 2 BRIGHTNESS Every step selected Lamps respond evenly Current matches step RECORD: steps 3 CONTROLS Local control Remote control Selector & interlocks RECORD: controls 4 MONITORING Status indications Alarm responses Fail-safe behaviour RECORD: alarms 5 SEQUENCES Flashing & sequence Stop-bar selection Where fitted RECORD: modes FUNCTION VERIFIED EVERY CIRCUIT · EVERY MODE 6 DEFECT ISOLATE · FIX · RE-TEST PASSED READY FOR INTEGRATION SCHEMATIC · CHECKS SHORTENED · NOT TO SCALE
operating check
record taken
defect
passed
The Fact Commissioning practice

Functional testing follows energisation. With the system live and stable, each circuit is operated the way it will be used: the right fixtures light, in the right colour and direction, every brightness step responds, and every control point works.

Indications, alarms and operating modes are checked too, and each result is recorded. A defect is isolated, fixed and re-tested. When the checks pass, the system is ready for integration. Light output is not measured here; that is a separate photometric exercise.

  1. Circuits. Select each circuit; confirm the right fixtures light, in colour and direction.
  2. Brightness. Step through every setting and confirm even response.
  3. Controls. Operate from each local and remote control point.
  4. Monitoring. Check status indications and alarm responses.
  5. Sequences. Test flashing, sequencing and stop-bar selection where fitted.
  6. Record. Log each result; isolate, fix and re-test any defect.
Purpose Prove every circuit, step and control works as designed
Circuit state Live; normal operating conditions
Checks Circuits, brightness steps, controls, indications, modes
Output Functional test record per circuit
Follows Energisation
Reference ICAO Doc 9157 Pt 5; ICAO Annex 14 Vol I Ch 8; FAA AC 150/5340-26; project specification
Schematic — checks shortened for clarity. The test list, acceptance criteria and witnesses are set by the project specification, the applicable standard and the equipment manufacturer’s instructions. Live work follows your site’s permit-to-work procedure. Secondary-power changeover is proved at the next stage, System Integration, against the switch-over times in ICAO Annex 14 Vol. I, Chapter 8. Where fitted, CCR protection and alarm functions (open-circuit, overcurrent, earth-fault) are checked only by the method in the CCR manufacturer’s test procedure, by simulation or a test facility, and never by opening a live loop.
Entry 23 · Energization Entry 25 · System integration

Frequently Asked Questions

Q1What is functional testing in airfield ground lighting?

A set of operating checks on the energised system that prove it does what the design requires: each circuit lights the right fixtures, every brightness step responds, and controls, indications and operating modes work. It follows energisation.

Q2How is it different from energisation?

Energisation shows the circuit can run live safely and steadily. Functional testing goes further and checks that each circuit, step and control actually performs its intended function, the way operators will use it.

Q3What is normally tested?

Circuit selection, which fixtures light and in what colour and direction, each brightness step, local and remote control, selector switches and interlocks, status and alarm indications, and flashing, sequencing or stop-bar selection where the design includes them.

Q4Is photometric testing part of functional testing?

No. Functional testing confirms that lights come on correctly and respond to control. Measuring light intensity, beam and colour against the standard is a separate photometric exercise.

Q5Why test every control point?

Each control point, local or remote, has its own wiring, settings and priority. Operating from each one, as a controller would, exposes wiring, labelling and configuration errors that a single-point test would miss.

Q6What happens if a function fails?

The defect is recorded, the circuit is isolated, the cause is found and corrected, and the affected checks are repeated. The record shows the failure, the correction and the passing re-test.

Precision AGL Academy

See It. Understand It. Then Learn How to Engineer It.

Recognising an AGL system visually is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how each light, sign and circuit works as part of a complete airport lighting system, not just as an isolated diagram.

See. Understand. Apply. Engineer.