Division 07 · TWY · Taxiway Lighting System

Taxiway Lighting System Commissioning

Individually accepted taxiway fixtures are only the starting point. Division 07 commissions the complete taxiway lighting system — edge, centreline, clearance bars, exit lighting and rapid-exit lighting — as one integrated whole, verifying that circuits, cables, fixtures, connectors, current, intensity, switching, control, alarms and photometric performance all operate correctly together.

Philosophy: this division follows Division 06 — Runway Lighting System Commissioning — and applies the same overall approach: System Identification → Circuit Verification → Cable/Connector/Fixture Verification → Energization → Current → Intensity → Switching → Control → Alarm → Photometry → Functional Test → Acceptance. Division 05 answers whether an individual fixture is acceptable; Division 07 answers whether the complete taxiway lighting system operates correctly.

17
Topics in Division
06
Verification Groups (A–F)
05
Lighting Subsystems Commissioned
11
Chain-of-Acceptance Links

Commissioning Philosophy

Every taxiway lighting subsystem moves through the same underlying sequence, from system identification through to the integrated acceptance gate.

System ID
Circuit Verification
Cable / Connector / Fixture
Energization
Current
Intensity
Switching
Control
Alarm
Photometry
Functional Test
Acceptance
Edge, centreline & clearance-bar lighting Exit & rapid-exit lighting Circuit, cable & connector integrity Current, intensity & switching performance Control, alarm & photometric compliance

Chain of Acceptance

The taxiway lighting system is evaluated as a complete chain — every link has to hold before the system is accepted. Even if every individual fixture has passed Division 05, the system can still fail Division 07 on any one of these links.

LinkWhat It Confirms
Accepted FixturesIndividual edge, centreline, clearance-bar, exit and rapid-exit fixtures carry a valid Division 05 acceptance
Healthy CircuitPrimary and secondary circuit continuity and insulation satisfy the applicable procedure
Healthy CablesCable route, continuity, insulation, termination and joints are sound and traceable end to end
Healthy ConnectorsConnectors mate, lock, seal and carry current correctly at every transformer and joint
Correct CurrentCCR output and taxiway circuit current agree at every commanded intensity step
Correct IntensityThe intensity command reaches the complete system, not merely the CCR
Correct SwitchingON, OFF and intensity selection respond correctly with no unintended operation
Correct ControlLocal and remote control commands are correctly acknowledged with accurate status feedback
Correct AlarmsFault conditions are detected, indicated, and recover correctly on reset
Photometric ComplianceSystem-level photometric performance satisfies the applicable acceptance criterion
Accepted Taxiway Lighting SystemAll applicable results are recorded and the system is formally accepted

Before Testing Begins

Two conditions should be established before Division 07 commissioning of any taxiway lighting subsystem begins.

Division Boundaries

  • Division 05 establishes the detailed individual-fixture testing methodology; Division 07 confirms that accepted fixtures function correctly within the complete taxiway lighting system
  • Connector identification, continuity, contact, mating, locking and sealing also sit within the broader Cable & Connector Testing division
  • The complete ALCMS/SCADA/PLC control-system integration remains within the applicable dedicated control-system commissioning scope; Division 07 verifies the taxiway lighting system's response to those control commands
  • The dedicated photometry division establishes the detailed measurement methodology; Division 07 performs the taxiway system-level photometric verification

System-Level Independence

  • The system-level acceptance gate must remain independent of individual fixture acceptance
  • Incorrect circuit loading, cable insulation failure, connector failure, incorrect current or intensity response, switching failure, control-system failure, alarm failure or photometric non-compliance can each fail the system even with fully accepted fixtures
  • Any abnormal current or intensity result should trigger investigation of fixture, transformer, cable, connector, circuit loading and CCR operation before proceeding
  • No taxiway lighting subsystem is released to the integrated functional test until every applicable item in this division is closed

The 17 Topics

Grouped by commissioning focus, in the order each taxiway lighting subsystem is normally worked through — click any topic to expand its verification checks and acceptance criteria.

A

Lighting Subsystem Commissioning

5 topics
TC-TWY-001Taxiway Edge-Light Commissioning
Verification Checks
  • Verify correct fixture type, location, spacing, and identification
  • Verify correct orientation, circuit, and colour/configuration as applicable
  • Verify fixture illumination, intensity operation, switching, and control response
  • Confirm system traceability: CCR → Primary Circuit → Isolation Transformers → Connectors → Taxiway Edge Fixtures
  • Check for missing, incorrect, or dark fixture
  • Check for incorrect orientation, damaged fixture, or abnormal illumination
  • Check for incorrect circuit connection
Acceptance / Record

Acceptance Criteria: the complete edge-light system is verified end-to-end from CCR to fixture with correct illumination, intensity operation, and control response.

TC-TWY-002Taxiway Centreline-Light Commissioning
Verification Checks
  • Verify fixture identification, location, and spacing/configuration
  • Verify orientation, circuit identity, cable continuity, and insulation
  • Verify connector condition, fixture operation, current, and intensity steps
  • Verify switching, control, and functional check
  • Confirm correct operation at each applicable intensity setting
  • Check for dark fixtures, incorrect sequence, or uneven illumination
  • Check for incorrect intensity, intermittent operation, or circuit interruption
Acceptance / Record

Acceptance Criteria: centreline lighting operates correctly at every applicable intensity setting with no circuit interruption.

TC-TWY-003Clearance-Bar Commissioning
Verification Checks
  • Verify correct location, fixture arrangement, and circuit
  • Verify correct orientation and illumination
  • Verify switching, intensity, and control response
  • Verify alarm/status where applicable
  • Perform functional test: Command → Circuit Response → Clearance-Bar Illumination → Control Indication
Acceptance / Record

Acceptance Criteria: the clearance bar operates as intended under all applicable operating conditions, where installed.

TC-TWY-004Taxiway Exit-Light Commissioning
Verification Checks
  • Verify correct location, fixture type, and orientation
  • Verify correct circuit, cable, and connector
  • Verify illumination, switching, and intensity
  • Verify control and acceptance
Acceptance / Record

Acceptance Criteria: all applicable exit-light fixtures operate correctly and respond to the designated control commands, where provided.

TC-TWY-005Rapid-Exit Taxiway-Light Commissioning
Verification Checks
  • Verify correct rapid-exit location and fixture configuration
  • Verify fixture spacing, circuit identity, cable condition, and connector condition
  • Verify fixture operation, current, intensity, switching, and control
  • Perform integrated verification with the associated taxiway lighting system
Acceptance / Record

Acceptance Criteria: the rapid-exit lighting system operates correctly in conjunction with the associated taxiway lighting system, where provided.

B

Circuit & Component Testing

4 topics
TC-TWY-006Taxiway Circuit Testing
Verification Checks
  • Verify circuit identification and circuit continuity
  • Verify cable continuity and isolation transformer continuity
  • Verify connector continuity and circuit insulation
  • Verify primary and secondary circuit condition
  • Confirm circuit configuration against approved test sequence
  • Test sequence: Identify Circuit → Isolate → Continuity Test → Insulation Test → Review Results → Restore Circuit
  • Record circuit ID, test point, test method, measured result, acceptance criterion, and result
Hold Point

Hold Point: circuit insulation acceptance values are taken from the applicable project/manufacturer procedure, never an arbitrary universal figure.

TC-TWY-007Cable Testing
Verification Checks
  • Verify cable identification, route, continuity, and insulation
  • Verify cable termination, joints, and condition
  • Verify cable connection to transformer and to fixture
  • Confirm traceability: CCR → Primary Cable → Joint → Transformer → Secondary Lead → Fixture
  • Check for open circuit and insulation deterioration
  • Check for damaged cable, incorrect termination, or incorrect circuit
  • Check for poor joint or moisture-related deterioration
Acceptance / Record

Acceptance Criteria: the cable network is verified continuous, correctly insulated, and correctly traceable from CCR through to fixture.

TC-TWY-008Fixture Testing
Verification Checks
  • Verify fixture identification, type, rating, and mounting
  • Verify height where applicable, alignment, and orientation
  • Verify lens, prism where applicable, and lamp/LED module
  • Verify secondary lead, connector, and insulation where applicable
  • Verify continuity, illumination, and operation
Note

Division boundary: Division 05 establishes the detailed individual-fixture testing methodology — Division 07 confirms that accepted fixtures function correctly within the complete taxiway lighting system.

Acceptance / Record

Acceptance Criteria: fixtures are confirmed to function correctly within the integrated taxiway lighting system.

TC-TWY-009Connector Testing
Verification Checks
  • Verify correct connector and connector identification
  • Verify contact condition, continuity, and mating
  • Verify locking, sealing, and cable termination
  • Verify moisture condition and mechanical integrity
  • Check: Transformer → Connector → Fixture
  • Check: Cable → Joint/Connector → Transformer, where applicable
Acceptance / Record

Acceptance Criteria: connector assemblies are verified for continuity, contact, mating, locking, sealing, and mechanical integrity.

C

Electrical Performance

2 topics
TC-TWY-010Current Verification
Verification Checks
  • Verify CCR output current and taxiway circuit current
  • Verify current at each applicable intensity step and current stability
  • Verify agreement between CCR indication and measured condition
  • Record commanded step, measured current, acceptance criterion (project/manufacturer), and result for each intensity step
  • On abnormal current, investigate fixture, transformer, cable, and connector condition
  • On abnormal current, investigate circuit loading and CCR operation
Hold Point

Hold Point: any abnormal current result at any intensity step is investigated and resolved before proceeding.

TC-TWY-011Intensity-Step Verification
Verification Checks
  • Verify minimum intensity and intermediate intensities
  • Verify maximum intensity and correct step transition
  • Verify correct circuit current at each step
  • Verify correct fixture response and control indication
  • Test sequence: Select Intensity → Verify CCR → Verify Current → Observe Taxiway Lights → Record
Acceptance / Record

Acceptance Criteria: the test demonstrates that the intensity command reaches the complete taxiway lighting system, not merely the CCR.

D

Control & Alarm Systems

3 topics
TC-TWY-012Switching Verification
Verification Checks
  • Verify ON and OFF operation
  • Verify intensity selection
  • Verify local switching and remote switching where applicable
  • Verify correct switching response and correct indication
  • Confirm no unintended operation
  • Sequence: Command → CCR → Circuit → Fixture → Status
Acceptance / Record

Acceptance Criteria: switching functions are confirmed correct at every applicable point with no unintended operation.

TC-TWY-013Control-System Verification
Verification Checks
  • Verify local control and remote control
  • Verify ON/OFF command and intensity command
  • Verify status feedback and command acknowledgement
  • Verify control mode and interlocks where applicable
  • Perform integrated control test: Control Command → CCR Response → Taxiway Circuit Response → Fixture Response → Control-System Feedback
Note

The complete ALCMS/SCADA/PLC integration remains within the applicable dedicated control-system commissioning scope; Division 07 verifies the taxiway lighting system's response to those control commands.

Acceptance / Record

Acceptance Criteria: the taxiway lighting system responds correctly to all applicable control commands.

TC-TWY-014Alarm Verification
Verification Checks (Where Provided)
  • Verify circuit failure alarm and CCR alarm
  • Verify current abnormality alarm and equipment fault
  • Verify control-system alarm and communication failure
  • Verify lighting-system fault indication
  • Test: Fault Condition → Detection → Alarm → Local Indication → Remote Indication → Reset/Recovery
  • Record alarm type, test condition, indication, remote status, recovery, and result
Acceptance / Record

Acceptance Criteria: applicable alarms and fault indications are confirmed to detect, indicate, and recover correctly.

E

Photometric & Functional Verification

2 topics
TC-TWY-015Taxiway Lighting Photometric Verification
Verification Checks
  • Verify light intensity, distribution, and beam direction as applicable
  • Verify uniformity and fixture alignment effect
  • Verify intensity performance and system-level photometric compliance
  • Before testing, confirm fixture installation and alignment are complete
  • Before testing, confirm correct circuit operating and correct intensity selected
  • Before testing, confirm CCR output verified, photometric equipment calibrated, and test configuration established
  • Record taxiway ID, lighting system, test date/condition, intensity step, photometric equipment, calibration status, measurement points, results, acceptance criterion, and pass/fail
Note

The dedicated photometry division treats photometry as a technical activity in its own right, covering equipment verification, calibration, and detailed measurement methodology. Division 07 = taxiway system-level photometric verification.

Hold Point

Hold Point: photometric equipment calibration status is verified valid before any measurement is recorded.

TC-TWY-016System Functional Test
Verification Checks
  • Verify edge, centreline, clearance-bar, exit, and rapid-exit lighting operational status
  • Verify circuit, current, intensity, and switching for each subsystem as applicable
  • Verify circuit continuity, cable testing, connector testing, and current confirmed complete
  • Verify local control, remote control where applicable, intensity control, and status feedback
  • Verify alarm functions, fault indication, and recovery
  • Verify photometric verification completed, calibration verified, and results evaluated
Acceptance / Record

Acceptance Criteria: the complete integrated taxiway lighting system passes the functional test across every subsystem, electrical, control, alarm, and photometric requirement.

F

Final Acceptance

1 topic
TC-TWY-017Taxiway Acceptance Test
Acceptance Requirements
  • Installation Compliance: correct lighting configuration, fixture locations, fixture types, and circuit configuration
  • Electrical Integrity: circuit continuity, cable integrity, connector integrity, insulation condition, and correct current
  • Functional Performance: fixture operation, switching, intensity steps, and correct system response
  • Control: local control, remote control where applicable, status feedback, and command response
  • Alarm: fault detection, alarm indication, and recovery
  • Photometric Performance: applicable measurements completed and acceptance criteria satisfied
  • Record final status: PASS, FAIL, RETEST, CONDITIONAL, or N/A
Acceptance / Record

Acceptance Criteria (final logic): Accepted Fixtures + Healthy Circuit + Healthy Cables + Healthy Connectors + Correct Current + Correct Intensity + Correct Switching + Correct Control + Correct Alarms + Photometric Compliance = ACCEPTED TAXIWAY LIGHTING SYSTEM. The system-level acceptance gate remains independent of individual fixture acceptance.

Taxiway Commissioning Flow

Division 07 runs as a single continuous sequence per taxiway lighting system, from Division 05 fixture acceptance through to integrated system acceptance.

1
Fixture Acceptance Input

Confirm Division 05 fixture acceptance for all applicable fixtures.

2
System Identification

Identify the taxiway lighting system and its subsystem boundaries.

3
Edge-Light Commissioning

Commission the complete taxiway edge-light system.

4
Centreline & Clearance Bar

Commission centreline lighting and clearance bars where provided.

5
Exit & Rapid-Exit

Commission exit and rapid-exit taxiway lighting where provided.

6
Circuit & Cable Testing

Verify circuit and cable electrical integrity across the system.

7
Fixture & Connector Testing

Confirm fixture and connector condition within the integrated system.

8
Current Verification

Verify CCR output and circuit current at every intensity step.

9
Intensity-Step Verification

Confirm the intensity command reaches the complete system.

10
Switching & Control

Verify switching functions and local/remote control response.

11
Alarm & Photometric

Verify alarm/fault behaviour and system-level photometric performance.

12
Functional Test & Acceptance

Complete the integrated functional test and final taxiway acceptance test.

Quick Reference

A short checklist view and test view of Division 07. Confirm every criterion against the approved specification and the current standard.

Taxiway lighting commissioning checklist

A taxiway lighting commissioning checklist follows the division sequence. (1) Confirm fixtures have passed Division 05 and the system is identified against the drawing. (2) Verify taxiway edge, centreline, clearance-bar, exit and rapid-exit lighting for location, type and orientation. (3) Verify circuit identification, cables and connectors. (4) Verify CCR output and circuit current at each applicable intensity step. (5) Verify switching and control, local and remote. (6) Verify alarms where provided. (7) Verify photometric performance where required. (8) Run the system functional test and sign the taxiway acceptance test.

Taxiway lighting commissioning test

The taxiway lighting commissioning test proves the taxiway lighting works as one system. It checks that edge and centreline lighting give continuous guidance, that clearance bars and exit lighting operate on their own circuits, and that intensity steps and control commands give the expected response. Acceptance closes only when installation compliance, circuit and cable results, control and alarm behaviour and the system functional test are all documented.

Frequently Asked Questions

Quick answers about Division 07 — Taxiway Lighting System Commissioning in the AGL Testing & Commissioning Manual.

Q1What is Division 07 — Taxiway Lighting System Commissioning in the AGL Testing & Commissioning Manual?

Division 07 of the AGL Testing & Commissioning Manual covers Taxiway Lighting System Commissioning. Individually accepted taxiway fixtures are only the starting point. Division 07 commissions the complete taxiway lighting system — edge, centreline, clearance bars, exit lighting and rapid-exit lighting — as one integrated whole, verifying that circuits, cables, fixtures, connectors, current, intensity, switching, control, alarms and photometric performance all operate correctly together. It contains 17 topics (TC-TWY-001 to TC-TWY-017) organised into 6 groups (A–F), each topic with its own verification checks.

Q2What is the philosophy behind Division 07 — Taxiway Lighting System Commissioning?

This division follows Division 06 — Runway Lighting System Commissioning — and applies the same overall approach: System Identification → Circuit Verification → Cable/Connector/Fixture Verification → Energization → Current → Intensity → Switching → Control → Alarm → Photometry → Functional Test → Acceptance. Division 05 answers whether an individual fixture is acceptable; Division 07 answers whether the complete taxiway lighting system operates correctly.

Q3What is the step-by-step sequence in Division 07?

Every taxiway lighting subsystem moves through the same underlying sequence, from system identification through to the integrated acceptance gate. Steps: System ID → Circuit Verification → Cable / Connector / Fixture → Energization → Current → Intensity → Switching → Control → Alarm → Photometry → Functional Test → Acceptance. Focus areas: Edge, centreline & clearance-bar lighting; Exit & rapid-exit lighting; Circuit, cable & connector integrity; Current, intensity & switching performance; Control, alarm & photometric compliance.

Q4Which topics does Division 07 cover?

Division 07 has 17 topics in 6 groups. A — Lighting Subsystem Commissioning: Taxiway Edge-Light Commissioning, Taxiway Centreline-Light Commissioning, Clearance-Bar Commissioning, Taxiway Exit-Light Commissioning, Rapid-Exit Taxiway-Light Commissioning. B — Circuit & Component Testing: Taxiway Circuit Testing, Cable Testing, Fixture Testing, Connector Testing. C — Electrical Performance: Current Verification, Intensity-Step Verification. D — Control & Alarm Systems: Switching Verification, Control-System Verification, Alarm Verification. E — Photometric & Functional Verification: Taxiway Lighting Photometric Verification, System Functional Test. F — Final Acceptance: Taxiway Acceptance Test.

Q5What is the chain of acceptance in Division 07?

The taxiway lighting system is evaluated as a complete chain — every link has to hold before the system is accepted. Even if every individual fixture has passed Division 05, the system can still fail Division 07 on any one of these links. Accepted Fixtures: Individual edge, centreline, clearance-bar, exit and rapid-exit fixtures carry a valid Division 05 acceptance; Healthy Circuit: Primary and secondary circuit continuity and insulation satisfy the applicable procedure; Healthy Cables: Cable route, continuity, insulation, termination and joints are sound and traceable end to end; Healthy Connectors: Connectors mate, lock, seal and carry current correctly at every transformer and joint; Correct Current: CCR output and taxiway circuit current agree at every commanded intensity step; Correct Intensity: The intensity command reaches the complete system, not merely the CCR; Correct Switching: ON, OFF and intensity selection respond correctly with no unintended operation; Correct Control: Local and remote control commands are correctly acknowledged with accurate status feedback; Correct Alarms: Fault conditions are detected, indicated, and recover correctly on reset; Photometric Compliance: System-level photometric performance satisfies the applicable acceptance criterion.

Q6What must be in place before testing begins in Division 07?

Two conditions should be established before Division 07 commissioning of any taxiway lighting subsystem begins. Division Boundaries: Division 05 establishes the detailed individual-fixture testing methodology; Division 07 confirms that accepted fixtures function correctly within the complete taxiway lighting system; Connector identification, continuity, contact, mating, locking and sealing also sit within the broader Cable & Connector Testing division; The complete ALCMS/SCADA/PLC control-system integration remains within the applicable dedicated control-system commissioning scope; Division 07 verifies the taxiway lighting system's response to those control commands; The dedicated photometry division establishes the detailed measurement methodology; Division 07 performs the taxiway system-level photometric verification. System-Level Independence: The system-level acceptance gate must remain independent of individual fixture acceptance; Incorrect circuit loading, cable insulation failure, connector failure, incorrect current or intensity response, switching failure, control-system failure, alarm failure or photometric non-compliance can each fail the system even with fully accepted fixtures; Any abnormal current or intensity result should trigger investigation of fixture, transformer, cable, connector, circuit loading and CCR operation before proceeding; No taxiway lighting subsystem is released to the integrated functional test until every applicable item in this division is closed.

Q7What is the Taxiway Commissioning Flow in Division 07?

Division 07 runs as a single continuous sequence per taxiway lighting system, from Division 05 fixture acceptance through to integrated system acceptance. (1) Fixture Acceptance Input — Confirm Division 05 fixture acceptance for all applicable fixtures; (2) System Identification — Identify the taxiway lighting system and its subsystem boundaries; (3) Edge-Light Commissioning — Commission the complete taxiway edge-light system; (4) Centreline & Clearance Bar — Commission centreline lighting and clearance bars where provided; (5) Exit & Rapid-Exit — Commission exit and rapid-exit taxiway lighting where provided; (6) Circuit & Cable Testing — Verify circuit and cable electrical integrity across the system; (7) Fixture & Connector Testing — Confirm fixture and connector condition within the integrated system; (8) Current Verification — Verify CCR output and circuit current at every intensity step; (9) Intensity-Step Verification — Confirm the intensity command reaches the complete system; (10) Switching & Control — Verify switching functions and local/remote control response; (11) Alarm & Photometric — Verify alarm/fault behaviour and system-level photometric performance; (12) Functional Test & Acceptance — Complete the integrated functional test and final taxiway acceptance test.

Q8What is on a taxiway lighting commissioning checklist?

A taxiway lighting commissioning checklist covers fixture acceptance, edge, centreline, clearance-bar and exit lighting, circuit and cable verification, CCR current at each intensity step, switching and control, alarms where provided, photometric checks where required, the system functional test and the acceptance test.

Q9What does a taxiway lighting commissioning test prove?

A taxiway lighting commissioning test proves the taxiway lighting works as one system: continuous guidance from edge and centreline lighting, correct clearance-bar and exit operation, correct intensity steps and control response. It is closed only once the results are documented.

Go Further

Don't Just Commission the Taxiway. Understand How Guidance Becomes Continuous.

Taxiway lighting commissioning proves that centerline and edge guidance function as one continuous system.

Build the technical knowledge to understand intersection guidance, circuit segmentation, and how taxiway lighting integrates with ALCMS control for safe ground movement.

Commission with precision. Guide with confidence. Operate with certainty.