What is earthing inspection?

A close look at the bonds, clamps, earth pits, ground rods and conductor that give fault current and lightning a safe path to earth, checking for corrosion, damage and breaks before they are needed. An earth can look perfect and still be open.

EARTHING INSPECTION SAME EARTHING, SAME ROUTE, DIFFERENT CONDITION DEFECTS FOUNDSOUND EARTHING BASE CANCCR / SIGNEARTH PITBASE CANCCR / SIGNEARTH PIT BROKEN CONDUCTOR, CORRODED JOINT, LOOSE BONDCONTINUOUS CONDUCTOR, TIGHT CLAMPS, DRY PIT EARTHING INSPECTION SEQUENCE PreparePermit, record to handLook at surfaceCovers, bonds, diggingOpen the pitWater, link, clampCheck bondsLugs, clamps, leadsCheck the runConductor, jointsRecordPhoto, place, action Never open or disconnect an earth while the equipment is energised, and keep clear in a storm. SCHEMATIC · EARTHING LAYOUTS AND CHECKLISTS DIFFER BETWEEN SITES · NOT TO SCALE
defect found
sound earthing
water
The Fact Inspection practice

The earthing network is the bare conductor, ground rods and bonding leads laid along the series circuit. It gives fault current and lightning a low-resistance path to earth and keeps exposed metal safe to touch. It does nothing until the day it is needed, so it fails quietly: buried joints corrode, digging cuts conductors and clamps work loose, while everything still looks normal. Inspection checks that the path is physically there. The insulated series-circuit cable is not an earth path, so an earth contact found on it is a fault, not an earth.

1Look from the surface first

A lot can be seen without opening anything. Check the bonding leads on the CCR, signs, base cans and metal covers, and confirm each still touches the metalwork it is meant to protect. Check that earth-pit covers are present, sound and reachable, and look along the route for digging, erosion or new works, and for any exposed or lifted conductor. Work on the airfield only with the right permission and under the site’s safety rules.

2Look, do not disturb

An earth conductor can carry fault current, so an earth is never opened, loosened or disconnected while the equipment it protects is energised. Inspection looks and records; opening a pit or a test link is done under the permit and isolation your procedure requires, and nothing is worked on in a thunderstorm. In the pit, note water, silt or debris, then check the test link, the rod clamp and every lug and fastener for corrosion, looseness or damage.

Do
  • Look before touching anything
  • Photograph defects where they are
  • Log against position and circuit
Do not
  • Disconnect an earth with equipment energised
  • Assume a clean joint means low resistance
  • Leave a cut or missing earth unreported

3Record and act

Photograph each defect and log it against its position and circuit. Inspection shows what can be seen; continuity and ground-rod resistance tests prove the electrical condition, and cleaning, remaking and protecting joints is earthing maintenance. A cut conductor or a missing bond on exposed metalwork is raised promptly, because the equipment may be unprotected until it is put right. Close the pit and restore the circuit only as your procedure allows.

Check pointWhat to look for
Bonding leadsOn the CCR, signs, base cans and metal covers: present, undamaged, touching the metalwork, not stretched
Lugs and clampsCorrosion, looseness, cracked, burned or missing fasteners
Earth pit and coverCover present and sound, access clear, water or debris inside
Test linkIn place, closed, clean and labelled
Ground-rod connectionClamp tight, no heavy corrosion, rod head intact
Counterpoise conductorVisible runs intact: no cuts, exposed or lifted lengths
JointsCorroded, cracked or burned, wrong or mixed fittings
RouteSigns of digging, erosion or new works over the conductor
RecordDated photo, position, circuit, finding and action
Schematic: earthing layouts, conductor sizes, rod types, inspection intervals and defect categories differ between sites. Maintenance requirements are in ICAO Annex 14, Volume I, Chapter 10, with guidance in the Aerodrome Design Manual (Doc 9157), Part 5, FAA AC 150/5340-26 (maintenance) and FAA AC 150/5340-30 (installation and earthing details), so confirm details against your maintenance plan, the project design and the edition in force.
Entry 9 · Base-can inspection Entry 11 · Normal condition

Frequently Asked Questions

Q1Why is the earthing network inspected?

Earthing does nothing until a fault or lightning strike, so a failure stays hidden. Buried joints corrode, digging cuts conductors and clamps work loose, yet the system still looks normal. Inspection checks that the path to earth is physically there and in good condition before it is needed.

Q2Can earthing be inspected while the circuit is live?

The visible parts can be looked at from outside: bonding leads, covers, pit lids and signs of digging. An earth connection is never opened, loosened or disconnected while the equipment it protects is energised, and an earth conductor can carry fault current, so it is treated with care. Opening a pit or a test link is done under the permit and isolation your procedure requires.

Q3What defects should be looked for?

Look for corroded, cracked or burned joints, loose or missing clamps and fasteners, a bonding lead that is damaged, stretched or no longer touching the metalwork, a cut, exposed or lifted counterpoise conductor, a damaged or missing pit cover, water or debris in an earth pit, an open or missing test link and signs of excavation along the route.

Q4Is inspection the same as earthing testing or maintenance?

No. Inspection finds and records the visible condition. Testing measures bond continuity and ground-rod resistance, and maintenance cleans, remakes and protects the connections. A joint can look sound and still read high, so an inspection finding often leads to a test or a repair, and a clean inspection does not replace testing.

Q5What happens after a defect is found?

Photograph it, log it against the position and circuit, and raise the test, repair or replacement. A cut conductor or a missing bond on exposed metalwork is raised promptly, because the equipment may not be protected until it is put right.

Precision AGL Academy

See It. Understand It. Then Learn How to Engineer It.

Recognising an AGL system visually is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how each light, sign and circuit works as part of a complete airport lighting system, not just as an isolated diagram.

See. Understand. Apply. Engineer.