Division 17 of 25 · Failure Database

Testing & Commissioning Failures

The dedicated failure-classification section for AGL testing, verification, commissioning and acceptance activities — connecting the Failure Database directly with the AGL Testing & Commissioning Manual. Covers electrical testing, functional and photometric performance, cable and connector testing, control and system integration, FAT/SAT, test-equipment calibration and commissioning control across 20 failure categories.

20 / 20
Topics Published
TCF-01 → 20
Failure ID Range
6 Groups
Electrical · Functional · Cable/Connector · Control/Integration · Equipment/Data · Retest
Rev 0
Initial Issue

Key principle — A system can appear operational during a normal visual inspection while still failing an electrical, photometric, alignment, functional, integration or acceptance test. Division 17 creates a structured path from Test → Test Result → Failure → Investigation → Corrective Action → Retest → Acceptance.

Diagnostic principle — Not every failed test is an equipment failure. Some findings originate from test equipment, calibration, test procedure, measurement error, configuration or the commissioning process rather than the AGL asset itself — always establish which side of that line a finding sits on before it is logged as a technical failure.

Division 17 · Testing & Commissioning Failure Topics

20 of 20 topics published
A
Electrical Testing Failures
5 topics
TCF-01 Insulation-Resistance Test Failure
Failure Definition

An insulation-resistance test does not achieve the applicable acceptance criterion.

Possible Areas Involved
  • Primary AGL cable
  • Secondary wiring
  • Equipment wiring
  • Transformer-associated circuits
  • Panels
  • Other electrical circuits
Possible Causes
  • Cable insulation deterioration
  • Moisture ingress
  • Cable damage
  • Contamination
  • Incorrect termination
  • Ageing
Investigation — Check
  • Test voltage
  • Test equipment
  • Test leads/connections
  • Circuit under test
  • Cable condition
  • Moisture
  • Previous test trend
Failure Chain
INSULATION DETERIORATION/MOISTURELOW INSULATION RESISTANCETEST FAILURECIRCUIT UNAVAILABLE/UNSUITABLE FOR ACCEPTANCE
TCF-02 Continuity-Test Failure
Failure Definition

Required electrical continuity cannot be demonstrated during testing.

Possible Causes
  • Open circuit
  • Broken conductor
  • Loose connection
  • Connector failure
  • Incorrect wiring
  • Termination failure
Investigation — Trace
TEST POINTCONDUCTORJOINT/CONNECTORTERMINATIONEQUIPMENT
Important Distinction

A continuity-test failure is a test finding. The underlying failure should subsequently be classified under the appropriate technical division, such as cable, connector or wiring failure.

TCF-03 Earth-Resistance Test Failure
Failure Definition

Measured earth resistance does not meet the applicable acceptance criterion.

Possible Causes
  • Earth-electrode deterioration
  • Poor connection
  • Corrosion
  • Broken earth conductor
  • Poor bonding
  • Incorrect earthing installation
  • Ground-condition changes
Investigation — Check
  • Test method
  • Test equipment
  • Earth electrode
  • Earth conductor
  • Bonding
  • Earth-pit condition
  • Historical measurements
Cross-Reference

Cross-reference Division 15 — Earthing & Bonding Failures.

TCF-04 Transformer-Test Failure
Failure Definition

An isolation transformer or associated transformer does not pass the applicable testing requirements.

Possible Areas
  • Insulation
  • Continuity
  • Electrical characteristics
  • Primary/secondary condition
  • Physical condition
Possible Causes
  • Winding failure
  • Insulation breakdown
  • Moisture
  • Connector failure
  • Internal damage
  • Incorrect installation
Cross-Reference

Cross-reference Division 04 — Isolation Transformer Failures.

TCF-05 CCR-Test Failure
Failure Definition

A Constant Current Regulator does not meet the applicable testing requirements.

Possible Test Areas
  • Output current
  • Regulation
  • Intensity steps
  • Protection
  • Alarm
  • Control
  • Communication
  • Functional operation
Possible Causes
  • CCR internal failure
  • Calibration drift
  • Controller failure
  • Thyristor/power-stage issue
  • Protection problem
  • Communication/control problem
Cross-Reference

Cross-reference Division 03 — CCR Failures.

B
Functional & Performance Testing
4 topics
TCF-06 Functional-Test Failure
Failure Definition

AGL equipment or system does not perform its intended function during functional testing.

Examples
  • Fixture does not illuminate
  • Stop bar does not operate correctly
  • RGL does not flash correctly
  • Sign does not operate
  • Circuit does not switch
  • Control command does not execute
Investigation

Determine whether the failure originates from:

EQUIPMENTELECTRICAL CIRCUITCONTROLCOMMUNICATIONCONFIGURATIONINSTALLATION
TCF-07 Photometric-Test Failure
Failure Definition

Lighting equipment or system does not satisfy the applicable photometric-performance requirements during testing.

Possible Areas
  • Intensity
  • Distribution
  • Uniformity
  • Alignment-related output
  • Optical performance
  • Colour-related performance where applicable
Possible Causes
  • Fixture degradation
  • LED/lamp failure
  • Optical contamination
  • Misalignment
  • Incorrect installation
  • Driver problem
Important Principle

A fixture can pass a functional ON/OFF test but fail a photometric test. Therefore these must remain separate failure categories.

TCF-08 PAPI Alignment Failure
Failure Definition

PAPI/APAPI installation does not satisfy the required alignment/elevation/orientation criteria during testing.

Possible Causes
  • Fixture movement
  • Foundation settlement
  • Incorrect installation
  • Structural movement
  • Alignment error
  • Incorrect adjustment
Investigation — Check
  • PAPI unit position
  • Elevation
  • Azimuth
  • Beam setting
  • Foundation
  • Mounting
  • Alignment references
Cross-Reference

Cross-reference Division 11 — PAPI/APAPI Failures.

TCF-09 Sign Acceptance-Test Failure
Failure Definition

An airfield sign does not satisfy the applicable acceptance-test requirements.

Possible Test Areas
  • Illumination
  • Brightness
  • Colour
  • Uniformity
  • Electrical operation
  • Message/legend
  • Structural condition
  • Functional operation
Possible Causes
  • LED/driver failure
  • Electrical failure
  • Incorrect installation
  • Optical problem
  • Message/component damage
Cross-Reference

Cross-reference Division 12 — Airfield Sign Failures.

C
Cable & Connector Testing
2 topics
TCF-10 Cable-Test Failure
Failure Definition

A cable does not pass the applicable electrical or installation test.

Possible Tests
  • Continuity
  • Insulation resistance
  • Fault identification
  • Other applicable cable tests
Possible Causes
  • Insulation breakdown
  • Open circuit
  • Short circuit
  • Earth fault
  • Mechanical damage
  • Moisture ingress
  • Termination failure
Cross-Reference

Cross-reference Division 02 and Division 05.

TCF-11 Connector-Test Failure
Failure Definition

A connector or connector assembly does not pass the applicable testing/verification requirement.

Possible Causes
  • Poor contact
  • Loose connector
  • Corrosion
  • High contact resistance
  • Incorrect installation
  • Moisture
  • Connector damage
Investigation — Check
  • Physical condition
  • Contact condition
  • Connection integrity
  • Installation
  • Sealing
  • Electrical continuity
Cross-Reference

Cross-reference Division 05 — Cable & Connector Failures.

D
Control & Integration Testing
5 topics
TCF-12 ALCMS Integration-Test Failure
Failure Definition

The ALCMS does not successfully integrate with the AGL equipment/control system during testing.

Possible Failure Areas
  • Communication
  • Status indication
  • Command execution
  • Alarm transmission
  • Equipment feedback
  • Network communication
Possible Causes
  • Configuration mismatch
  • Communication failure
  • PLC/SCADA problem
  • Incorrect addressing
  • Software/configuration error
  • Interface problem
Investigation — Verify
AGL EQUIPMENTLOCAL CONTROLCOMMUNICATION NETWORKALCMSOPERATOR INTERFACEFEEDBACK/STATUS
Cross-Reference

Cross-reference Division 07 — Control System Failures.

TCF-13 FAT Failure
Failure Definition

Equipment or system does not satisfy the applicable requirements during Factory Acceptance Testing.

Typical Application
  • CCR
  • ALCMS
  • Airfield signs
  • Control panels
  • Other supplied equipment/system assemblies
Possible Causes
  • Design issue
  • Manufacturing defect
  • Configuration error
  • Software problem
  • Functional deficiency
  • Documentation discrepancy
Investigation — Record
  • FAT test item
  • Requirement
  • Actual result
  • Failure
  • Corrective action
  • Retest result
TCF-14 SAT Failure
Failure Definition

Equipment or system does not satisfy the applicable requirements during Site Acceptance Testing.

Possible Causes
  • Installation problem
  • Wiring error
  • Configuration issue
  • Site condition
  • Equipment defect
  • Integration problem
  • Commissioning error
Important Distinction

FAT failure primarily identifies a failure during factory verification. SAT failure identifies a failure during site acceptance. They should not be merged into one category.

TCF-15 System Integration Failure
Failure Definition

Two or more AGL subsystems do not operate correctly together during integration testing.

Examples
  • CCR ↔ ALCMS
  • ALCMS ↔ control system
  • Lighting system ↔ monitoring
  • PAPI ↔ associated control/monitoring
  • Sign system ↔ control system
Possible Causes
  • Interface mismatch
  • Configuration error
  • Communication failure
  • Incorrect addressing
  • Control logic problem
  • Wiring problem
Investigation

Identify whether the failure originates at:

SUBSYSTEM AINTERFACECOMMUNICATIONSUBSYSTEM B
TCF-16 Performance Acceptance Failure
Failure Definition

The completed system does not meet the required performance criteria during acceptance.

Potential Areas
  • Electrical performance
  • Lighting performance
  • Photometric performance
  • Control performance
  • System response
  • Functional performance
Important Distinction

A system can pass individual component tests but fail system-level performance acceptance. This is why the category remains separate:

INDIVIDUAL FIXTURES PASSCIRCUIT PASSESCONTROL PASSESCOMPLETE SYSTEM FAILS PERFORMANCE REQUIREMENT
E
Test Equipment & Data Quality
2 topics
TCF-17 Calibration Failure
Failure Definition

Test equipment or measurement instrumentation is found to have invalid, expired or otherwise unacceptable calibration status for the intended test.

Possible Causes
  • Calibration expiry
  • Calibration drift
  • Damaged instrument
  • Incorrect calibration certificate
  • Wrong instrument used
  • Instrument out of tolerance
Consequences
  • Test result validity may be compromised
  • Retesting may be required
  • Previous test results may require review
Investigation — Check
  • Instrument ID
  • Calibration certificate
  • Calibration validity
  • Test range
  • Instrument condition
  • Test procedure
Cross-Reference

Cross-reference Division 25 — Test Equipment, Calibration & Engineering Quality.

TCF-18 Incorrect Test Result
Failure Definition

A test result is determined to be incorrect, invalid or inconsistent with the actual condition of the equipment/system.

Possible Causes
  • Incorrect test procedure
  • Incorrect test setup
  • Instrument error
  • Calculation error
  • Data-entry error
  • Incorrect test point
  • Incorrect interpretation
Important Principle

An incorrect test result is not automatically an equipment failure. The investigation must establish whether the problem was equipment failure, or testing/measurement failure.

F
Retest & Commissioning Control
2 topics
TCF-19 Failed Retest
Failure Definition

Equipment/system remains non-compliant or unsuccessful after corrective action and subsequent retesting.

Possible Causes
  • Root cause not correctly identified
  • Incomplete corrective action
  • Incorrect replacement component
  • Secondary fault
  • Test-method problem
  • Recurring failure
Reliability Significance

A failed retest should trigger deeper RCA, rather than repeated corrective actions without identifying the underlying cause.

INITIAL TEST FAILUREREPAIRRETEST FAILURERCA ESCALATIONCORRECTIVE ACTION REVISIONFINAL RETEST
TCF-20 Commissioning Deviation
Failure Definition

A deviation from the approved commissioning requirement, procedure, design, specification, sequence or acceptance condition.

Examples
  • Approved test sequence not followed
  • Installation differs from approved design
  • Required test unavailable
  • Component substitution
  • Outstanding punch-list item
  • Test condition differs from approved requirement
Investigation — Record
  • Requirement
  • Actual condition
  • Deviation
  • Technical justification
  • Risk assessment where applicable
  • Approval
  • Corrective action
  • Closure status
Important Distinction

A commissioning deviation does not necessarily mean the equipment itself has failed. It means the commissioning condition or process has deviated from the approved requirement.

No topics match your search.

Division-Wide Requirements

Diagnostic matrix, failure chains, the test-failure-vs-equipment-failure principle, structured failure record and severity linkage that apply across all 20 Division 17 Testing & Commissioning failure topics.

A. Testing & Commissioning Diagnostic Matrix

Quick-reference mapping of each failure to its primary investigation focus:

FailurePrimary Investigation
Insulation-resistance test failureInsulation/cable condition
Continuity-test failureElectrical continuity
Earth-resistance test failureEarth system
Transformer-test failureTransformer condition
CCR-test failureCCR performance
Functional-test failureFunctional operation
Photometric-test failureOptical/photometric performance
PAPI alignment failurePAPI geometry/alignment
Sign acceptance-test failureSign performance
Cable-test failureCable condition
Connector-test failureConnector condition
ALCMS integration-test failureControl/integration
FAT failureFactory acceptance
SAT failureSite acceptance
System integration failureSubsystem interfaces
Performance acceptance failureOverall system performance
Calibration failureTest-equipment validity
Incorrect test resultMeasurement/data validity
Failed retestCorrective-action effectiveness
Commissioning deviationCompliance with commissioning requirements

B. Testing & Commissioning Failure Chains

Record the full test-to-acceptance chain, not just the final pass/fail result.

Chain 1 — Cable
CABLE INSULATION DETERIORATIONINSULATION-RESISTANCE TEST FAILURECABLE INVESTIGATIONCABLE REPAIR/REPLACEMENTRETESTACCEPTANCE
Chain 2 — Earth
EARTH-ELECTRODE/CONNECTION DETERIORATIONHIGH EARTH RESISTANCEEARTH-RESISTANCE TEST FAILUREEARTHING CORRECTIVE ACTIONRETESTACCEPTANCE
Chain 3 — Photometry
FIXTURE MISALIGNMENT/OPTICAL DEGRADATIONPHOTOMETRIC-TEST FAILUREALIGNMENT/OPTICAL CORRECTIVE ACTIONPHOTOMETRIC RETESTPERFORMANCE ACCEPTANCE
Chain 4 — Control
CONFIGURATION/COMMUNICATION PROBLEMALCMS INTEGRATION-TEST FAILURECONFIGURATION/INTERFACE CORRECTIONINTEGRATION RETESTSYSTEM ACCEPTANCE
Chain 5 — FAT/SAT
EQUIPMENT/CONFIGURATION ISSUEFAT FAILUREFACTORY CORRECTIVE ACTIONFAT RETESTSHIPMENT/SITE INSTALLATIONSAT
Chain 6 — Failed Retest
INITIAL TEST FAILURECORRECTIVE ACTIONFAILED RETESTRCA ESCALATIONREVISED CORRECTIVE ACTIONSUCCESSFUL RETESTFINAL ACCEPTANCE

C. Test Failure vs. Equipment Failure

This distinction is built into the Failure Database — every Division 17 record should separate the testing failure from the technical failure it reveals (or fails to reveal):

Scenario 1

Cable insulation breakdown → Insulation-resistance test failure. The technical failure is the cable insulation breakdown; the testing failure is the insulation-resistance test failure.

Scenario 2

Incorrect test setup → Incorrect test result. Here the equipment may actually be healthy — the failure is associated with the testing process, not necessarily the AGL equipment.

Scenario 3

PAPI physically misaligned → PAPI alignment failure → PAPI alignment test failure. Division 11 records the physical/technical PAPI failure; Division 17 records the testing/commissioning failure. This cross-linking is important.

D. Failure Severity

Every failure receives a severity classification, plus operational-impact tagging:

Critical / Safety-Critical — immediate operational or safety risk

Major / Operationally Critical — significant availability impact

Moderate — reduced performance, not yet critical

Minor / Non-Critical — limited or no operational effect

Degradation / Intermittent / Latent — developing or hidden fault

E. Testing & Commissioning Failure Record

Every Division 17 failure should have a structured record containing at minimum:

Test Identification

  • Failure ID
  • Airport
  • Project
  • Asset ID
  • System/Subsystem
  • Test Type
  • Test Procedure/Reference
  • Test Date
  • Tester
  • Test Location

Test Equipment

  • Instrument ID
  • Instrument Type
  • Calibration Status
  • Calibration Validity
  • Test Range
  • Test Setup

Test Requirement

  • Test Parameter
  • Acceptance Criterion
  • Required Value/Range
  • Actual Measured Result

Failure

  • Failure Category
  • Failure Mode
  • Pass/Fail Status
  • Extent of Failure
  • Immediate Cause
  • Underlying Technical Failure

Investigation

  • Test-Method Verification
  • Instrument Verification
  • Equipment Investigation
  • Installation Investigation
  • Configuration Investigation

Corrective Action

  • Repair
  • Adjustment
  • Replacement
  • Configuration Correction
  • Calibration Action
  • Documentation Correction

Retest

  • Retest Date
  • Retest Result
  • Retest Status
  • Number of Retests
  • Failed Retest if Applicable

Acceptance

  • Final Acceptance
  • Punch-List Status
  • Commissioning Deviation
  • Approval
  • Return-to-Service Status

Reliability

  • Repeat Failure
  • Root Cause
  • Corrective-Action Effectiveness
  • Lessons Learned
  • Preventive Action

F. Division 17 vs. the Technical Divisions

Division 17 is the quality-control bridge between the AGL equipment failure database and the AGL Testing & Commissioning Manual. A failed test is a finding, not automatically a verdict — always establish whether the root cause sits with the asset (cross-reference the relevant technical division — CCR, cable/connector, earthing, PAPI, signs, transformer, control system), the test process (procedure, setup, interpretation), or the test equipment (calibration, instrument condition). This prevents an important reliability-reporting error: counting every failed test as an equipment failure when some failures actually originate from test equipment, calibration, test procedure, measurement error, configuration or the commissioning process.

TEST/COMMISSIONING ACTIVITYASSET/SYSTEMTEST TYPETEST PARAMETERACCEPTANCE CRITERIONACTUAL RESULTFAILURE CLASSIFICATIONTECHNICAL ROOT CAUSECORRECTIVE ACTIONRETESTACCEPTANCECOMMISSIONING STATUSLESSONS LEARNED

Frequently Asked Questions

Quick answers about testing and commissioning failures, as covered in Division 17 of the AGL Failure Database.

Q1What is Division 17 — Testing & Commissioning Failures in the AGL Failure Database?

Division 17 covers failures in testing and commissioning, and links the Failure Database directly with the AGL Testing & Commissioning Manual. It contains 20 published topics (TCF-01 to TCF-20) covering electrical testing, functional and photometric performance, cable and connector testing, control and system integration, FAT/SAT, test-equipment calibration and commissioning deviations.

Q2Which testing and commissioning failures does Division 17 cover?

Insulation-resistance, continuity, earth-resistance, transformer and CCR test failures, functional-test and photometric-test failures, PAPI alignment failure, sign acceptance-test failure, cable-test and connector-test failures, ALCMS integration-test failure, FAT and SAT failures, system integration failure, performance acceptance failure, calibration failure, incorrect test result, failed retest and commissioning deviation.

Q3How are the 20 testing topics grouped?

They fall into six groups: Electrical Testing Failures (5 topics), Functional & Performance Testing (4), Cable & Connector Testing (2), Control & Integration Testing (5), Test Equipment & Data Quality (2) and Retest & Commissioning Control (2).

Q4Is a failed test the same as an equipment failure?

No. A failed test is a finding, not automatically a verdict. Every Division 17 record should separate the testing failure from the technical failure it reveals, or fails to reveal. A cable insulation breakdown produces an insulation-resistance test failure, but an incorrect test setup can produce an incorrect result while the equipment is healthy.

Q5Where can the root cause of a failed test sit?

It can sit with the asset (cross-referencing the relevant technical division), the test process (procedure, setup or interpretation) or the test equipment (calibration or instrument condition). Establishing which one applies prevents an incorrect verdict against the asset.

Q6What test-to-acceptance chains does Division 17 capture?

Division 17 records the full chain rather than the final pass or fail. In the cable chain, insulation deterioration leads to an insulation-resistance test failure, cable investigation, repair or replacement, retest and acceptance. The earth chain runs from electrode or connection deterioration through high earth resistance and an earth-resistance test failure to earthing corrective action, retest and acceptance. A photometry chain is also captured.

Q7What should be recorded for a testing or commissioning failure?

Records include test identification (failure ID, asset, system, test type, procedure reference, date, tester), test-equipment details (instrument ID, type, calibration status and validity, range and setup), test requirement (parameter, acceptance criterion, required and measured values) and failure information (category, mode, pass/fail status, extent).

Q8How are failure severity and operational impact classified?

Every failure receives a severity classification, plus operational-impact tagging. The classes are Critical / Safety-Critical (immediate operational or safety risk), Major / Operationally Critical (significant availability impact), Moderate (reduced performance, not yet critical), Minor / Non-Critical (limited or no operational effect), and Degradation / Intermittent / Latent (a developing or hidden fault).

Beyond the Failed Test

DON’T JUST RE-TEST. UNDERSTAND WHY THE FIRST RESULT WAS WRONG.

A test or commissioning failure can come from a genuine system fault, a test-method error, or an out-of-tolerance instrument — real troubleshooting means understanding testing procedure and acceptance criteria well enough to know which one it actually was.

Take that knowledge further with Precision AGL Academy.

Build Practical AGL Troubleshooting Skills

Learn how to connect:

Failure Symptoms System Understanding Investigation Root Cause Corrective Action Verification Recurrence Prevention

Develop structured knowledge across AGL fundamentals, components, electrical systems, testing, photometry, troubleshooting, maintenance and commissioning.

Find the failure. Understand the cause. Build the engineering skill.