Division 07 of 25 · COM Series

Commissioning & Baseline Asset Performance

The technical gateway between installation/handover and the operational lifecycle of the AGL asset. Division 06 establishes that the equipment has been installed, identified, documented and handed over — Division 07 proves that the installed asset performs correctly, establishes its initial measurable condition, and creates the baseline against which all future inspection, maintenance, testing, reliability and condition assessment will be judged.

19 / 19
Topics Scoped
COM-01 → 19
Topic ID Range
Baseline Gateway
Layer · Verification → Reference
Rev 0
Initial Issue

The question this division answers — Does the installed asset perform correctly, what is its verified starting condition, and what baseline values will every future inspection, test and condition assessment be compared against?

Where Division 07 Sits in the Lifecycle

Division 07 should be directly aligned with your AGL Testing & Commissioning Manual: the Manual defines how each measurement and commissioning test is performed, while the Asset Lifecycle Guide defines how the resulting verified values become the permanent baseline of the asset and are used throughout its life.

01–03 — Plan, Identify & Assess
04–06 — Design, Procure & Install
07 — Commission & Baseline
08 onward — Operate → Maintain → Monitor → Optimize → Replace → Dispose

Division 07 · Commissioning & Baseline Asset Performance Topics

19 of 19 topics scoped
COM-01 Commissioning Verification
Purpose

Confirms that the installed AGL system satisfies the approved design, specifications and commissioning requirements.

Verify
  • Correct equipment
  • Correct location
  • Correct configuration
  • Correct circuit
  • Correct wiring
  • Correct connections
  • Correct protection
  • Correct earthing
  • Correct control interfaces
  • Correct equipment identification
  • Correct operational response
  • Correct documentation
Verification Sequence
INSTALLATION COMPLETEVISUAL INSPECTIONELECTRICAL VERIFICATIONFUNCTIONAL TESTINGPERFORMANCE TESTINGDEFECT CORRECTIONRETESTINGCOMMISSIONING ACCEPTANCE
COM-02 Electrical Baseline
Purpose

Establishes the initial measured electrical condition of the AGL system.

Depending on the Asset, Record
  • Voltage
  • Current
  • Insulation resistance
  • Earth resistance
  • Continuity
  • Circuit resistance
  • Leakage/current characteristics
  • CCR output
  • Transformer electrical characteristics
  • Protection operation
  • Control signals
Importance
COMMISSIONING CURRENTPERIODIC CURRENTTRENDABNORMAL DEVIATIONINVESTIGATION

This converts testing from simply pass/fail into a lifecycle performance-management tool.

COM-03 Photometric Baseline
Purpose

Establishes the initial optical performance of the AGL system. This should be one of the strongest links between Division 07 and your AGL Photometry Testing Manual.

Depending on the System, Establish
  • Intensity
  • Photometric distribution
  • Horizontal/vertical performance where applicable
  • Beam characteristics
  • Alignment
  • Color/chromaticity where applicable
  • Uniformity
  • Light output
  • Compliance status
Applicable Assets

Runway lights, taxiway lights, approach lights, PAPI, and other photometrically controlled AGL systems.

Lifecycle Application
INITIAL PHOTOMETRYPERIODIC PHOTOMETRYPERFORMANCE TRENDDEGRADATION DETECTIONMAINTENANCE / REPLACEMENT DECISION
COM-04 Functional Baseline
Purpose

Establishes how the equipment behaves under normal operating conditions.

Record
  • Start/stop operation
  • Switching
  • Dimming
  • Control response
  • Monitoring
  • Alarm response
  • Fault indication
  • Interlocking
  • Remote control
  • Local control
  • Emergency functions
Example — AGL Lighting System
CONTROL COMMANDCCR RESPONSESERIES CIRCUIT RESPONSEFIXTURE OPERATIONMONITORING FEEDBACK

All stages should be verified.

COM-05 CCR Baseline
Purpose

Establishes the initial operating condition of each Constant Current Regulator.

Record
  • CCR Asset ID
  • Manufacturer
  • Model
  • Serial number
  • Rating
  • Circuit served
  • Input voltage
  • Output current
  • Output stages
  • Output regulation
  • Power factor, where applicable
  • Alarms
  • Protection
  • Control response
  • Monitoring response
  • Internal condition
  • Temperature/thermal observations where applicable
  • Test results
Operational Baseline

Record performance at the applicable brightness/current levels.

Lifecycle Use

Future CCR testing can compare baseline output against current output to identify performance deterioration.

COM-06 Transformer Baseline
Purpose

For each isolating transformer, establish the initial electrical and physical condition.

Record
  • Asset ID
  • Manufacturer
  • Model
  • Serial number
  • Rating
  • Primary/secondary information
  • Associated fixture
  • Circuit
  • Insulation resistance
  • Continuity
  • Visual condition
  • Connection condition
  • Test results
Lifecycle Purpose

The baseline provides a reference for identifying electrical deterioration, insulation degradation, abnormal performance and repeated failures.

COM-07 Cable Baseline
Purpose

The primary and associated cable system should have an initial verified condition.

Record
  • Cable ID
  • Circuit
  • Route
  • Length
  • Cable type
  • Cable size
  • Insulation resistance
  • Continuity
  • Earth/ground-related test results as applicable
  • Joint locations
  • Termination details
  • Test equipment
  • Test date
  • Tester
  • Test result
Important

The cable baseline should be associated with the specific circuit rather than treated as an isolated test document.

COM-08 Fixture Baseline
Purpose

Each relevant AGL fixture should have a verified initial condition.

Record
  • Asset ID
  • Fixture type
  • Manufacturer
  • Model
  • Serial number
  • Location
  • Circuit
  • Transformer
  • Physical condition
  • Optical condition
  • Alignment
  • Electrical condition
  • Photometric performance
  • Installation condition
  • Photographs
  • Test result
Baseline Objective
What does a healthy newly commissioned fixture look and perform like?
COM-09 PAPI Baseline
Purpose

PAPI requires a particularly controlled commissioning baseline.

Record
  • PAPI asset ID
  • Unit identification
  • Manufacturer
  • Model
  • Serial number
  • Runway
  • Location
  • Alignment
  • Elevation-related settings
  • Optical performance
  • Visual indication
  • Electrical condition
  • Control functions
  • Alarm functions
  • Photometric test results
  • Installation photographs
Lifecycle Importance

Future PAPI inspection and photometric/alignment testing can be compared against the original commissioning condition.

COM-10 Sign Baseline
Purpose

Establish the initial condition and performance of illuminated airfield signs.

Record
  • Sign Asset ID
  • Sign designation
  • Manufacturer
  • Model
  • Serial number
  • Location
  • Circuit
  • Electrical performance
  • Illumination condition
  • Legends
  • Physical condition
  • Structural condition
  • Visibility
  • Control response
  • Photographs
  • Test results
COM-11 ALCMS Baseline
Purpose

Establish the initial condition of the monitoring and control system.

Record
  • System configuration
  • Hardware
  • Software version
  • Controller configuration
  • Communication interfaces
  • Network configuration
  • CCR interfaces
  • Alarm points
  • Status indications
  • Control commands
  • Remote/local operation
  • Data logging
  • Time synchronization
  • User/access configuration where appropriate
  • Backup configuration
  • Initial system health
Important

For software-controlled systems, record the version/configuration baseline. Future changes can then be compared against the original commissioned configuration.

COM-12 Energy Baseline
Purpose

Establishes the initial energy performance of the AGL system.

Depending on the System, Record
  • Power consumption
  • CCR input power
  • Circuit power
  • Operating current
  • Operating hours
  • Energy consumption
  • Brightness level
  • Power factor where applicable
Lifecycle Use

Energy-performance monitoring, efficiency analysis, abnormal consumption detection, upgrade evaluation and lifecycle-cost analysis.

COM-13 Operational Baseline
Purpose

Establishes how the AGL system performs during actual operational use.

Consider
  • Normal operating modes
  • Brightness levels
  • Switching
  • ATC/ALCMS interface
  • Operational response
  • Alarm response
  • Availability
  • Response time
  • Abnormal condition handling
Example
COMMAND ISSUEDCONTROL SYSTEM RESPONDSCCR RESPONDSSERIES CIRCUIT OPERATESFIXTURE OPERATESMONITORING CONFIRMS STATUS

This provides a complete operational baseline rather than only component-level test results.

COM-14 Initial Reliability Baseline
Purpose

Establishes the starting point for future reliability analysis. At commissioning, there may not yet be enough operational history to calculate meaningful long-term failure rates — so the initial reliability parameters and assumptions are recorded instead.

Record
  • Equipment type
  • Manufacturer
  • Model
  • Criticality
  • Expected service life
  • Reliability data supplied by manufacturer
  • Known failure modes
  • Warranty period
  • Spare availability
  • Redundancy
  • Single points of failure
  • Initial defects
  • Commissioning failures, if any
Later

Operational history can progressively establish failure rate, MTBF, MTTR, repeat failures and reliability trend — linking Division 07 to your later Failure Database & Reliability Engineering functions.

COM-15 Initial Condition Assessment
Purpose

Establishes the physical and technical condition immediately after commissioning.

Assess
  • Physical — damage, corrosion, contamination, mechanical condition
  • Electrical — connections, insulation, earthing, electrical performance
  • Optical — lens, light output, alignment, photometric performance
  • Civil — base can, mounting, foundation, drainage, surrounding surface
  • Documentation — asset identification, as-built, test records, manuals
Condition Categories

A controlled condition-rating system can be used, for example:

RatingCategory
1Excellent
2Good
3Fair
4Poor
5Critical

This matches the condition scale established in the Division 02 asset register (REG-12), so ratings are directly comparable across the Guide.

COM-16 Baseline Test Records
Purpose

Every baseline measurement should have a controlled test record.

Minimum Fields
  • Asset ID
  • Equipment
  • Test type
  • Test date
  • Location
  • Operating condition
  • Test procedure/reference
  • Test equipment
  • Test-equipment ID
  • Calibration status
  • Test parameter
  • Measured value
  • Acceptance criterion
  • Result
  • Inspector/tester
  • Remarks
  • Photographs where required
  • Related document
Example
FieldValue
AssetCCR-01
TestOutput Current
StageCommissioning
MeasuredRecorded value
RequiredApproved criterion
ResultPass
Test EquipmentCalibrated instrument
DateCommissioning date
COM-17 Baseline Performance Report
Purpose

Consolidates the commissioning results into a single controlled lifecycle document.

Recommended Report Structure
  • A. Asset Identification — Asset ID, equipment, manufacturer, model, serial number, location
  • B. Installation — installation date, commissioning date, project, contractor, as-built reference
  • C. Electrical Performance — electrical, CCR, transformer and cable results
  • D. Photometric Performance — fixture, PAPI and relevant photometric measurements
  • E. Functional Performance — controls, monitoring, alarms, switching, dimming
  • F. Energy Performance — initial energy measurements
  • G. Condition — initial condition rating, photographs, defects
  • H. Reliability — initial reliability information
  • I. Acceptance — acceptance status, outstanding actions
  • J. Lifecycle Baseline — final approved baseline values
COM-18 Asset Acceptance Criteria
Purpose

Asset acceptance criteria should be defined before commissioning begins.

Acceptance Should Cover
  • Installation compliance
  • Electrical compliance
  • Functional compliance
  • Photometric compliance
  • Control/monitoring compliance
  • Safety compliance
  • Documentation completeness
  • As-built completeness
  • Asset identification
  • Baseline establishment
  • Defect closure
Possible Acceptance Outcomes
OutcomeMeaning
AcceptedAll required criteria satisfied
Conditionally AcceptedMinor controlled outstanding items remain
Rejected / Not AcceptedOne or more critical acceptance requirements are not satisfied

Acceptance status should be formally documented.

COM-19 Post-Commissioning Asset Status
Purpose

After successful commissioning, the asset should move to a defined lifecycle status.

Recommended Status Transition
PLANNEDPROCUREDINSTALLEDUNDER COMMISSIONINGCOMMISSIONING COMPLETEOPERATIONAL / ACCEPTEDUNDER MAINTENANCECONDITION MONITORINGREHABILITATION / UPGRADEREPLACEMENTDECOMMISSIONED
Important

This status should be reflected in the asset register.

No topics match your search.

Division 07 Master Structure

All 19 topics at a glance, with the core question each one answers.

#TopicCore Question
01Commissioning VerificationIs the correct equipment installed, connected and documented?
02Electrical BaselineWhat is the initial measured electrical condition?
03Photometric BaselineWhat is the initial optical/photometric performance?
04Functional BaselineHow does the equipment behave under normal operation?
05CCR BaselineWhat is the initial operating condition of each CCR?
06Transformer BaselineWhat is the initial condition of each isolating transformer?
07Cable BaselineWhat is the initial verified condition of the cable system?
08Fixture BaselineWhat does a healthy newly commissioned fixture look like?
09PAPI BaselineWhat is the verified original commissioning condition of the PAPI?
10Sign BaselineWhat is the initial condition of illuminated airfield signs?
11ALCMS BaselineWhat is the initial configuration of the monitoring/control system?
12Energy BaselineWhat is the initial energy performance of the system?
13Operational BaselineHow does the system perform during actual operational use?
14Initial Reliability BaselineWhat are the starting reliability parameters and assumptions?
15Initial Condition AssessmentWhat is the physical/technical condition right after commissioning?
16Baseline Test RecordsIs every baseline measurement backed by a controlled test record?
17Baseline Performance ReportWhere do all baseline results get consolidated?
18Asset Acceptance CriteriaWhat must be true before the asset is formally accepted?
19Post-Commissioning Asset StatusWhat lifecycle status does the asset move to next?

Key Deliverables

The mandatory outputs of Division 07.

AGL Commissioning Verification Procedure
AGL Electrical Baseline Record
AGL Photometric Baseline Record
AGL Functional Baseline Record
AGL CCR Commissioning Baseline
AGL Transformer Commissioning Baseline
AGL Cable Commissioning Baseline
AGL Fixture Commissioning Baseline
AGL PAPI Commissioning Baseline
AGL Sign Commissioning Baseline
AGL ALCMS Commissioning Baseline
AGL Energy Baseline Record
AGL Operational Baseline Record
AGL Initial Reliability Baseline
AGL Initial Asset Condition Assessment
AGL Baseline Test Record
AGL Baseline Performance Report
AGL Asset Acceptance Criteria
AGL Post-Commissioning Asset Status Record

Most Important Design Principle

Division 07 should remain the technical gateway between installation/handover and the operational lifecycle of the AGL asset. It does not install the equipment (Division 06) and it does not run day-to-day operations (Division 08) — it proves the installed asset performs correctly and freezes its verified starting condition as the permanent baseline.

The commissioning baseline is the birth certificate of an operational AGL asset. At commissioning, the airport should know what asset is installed, where it is installed, its initial condition, how it performs electrically, photometrically and functionally, how much energy it consumes, its initial reliability expectation, what documentation supports it, its approved baseline values, and whether it has been formally accepted.

Division 04 — Lifecycle Design
Division 05 — Lifecycle Procurement
Division 06 — Installation & Handover
Division 07 — Commissioning & Baseline Performance
Division 08 onward — Operations → Inspection & Testing → Preventive Maintenance → Failure Analysis → Reliability Engineering → Condition Assessment → Lifecycle Renewal/Replacement

This is also why Division 07 should be tightly synchronized with your AGL Testing & Commissioning Manual: the Manual defines how each measurement and commissioning test is performed, while the Asset Lifecycle Guide defines how the resulting verified values become the permanent baseline of the asset and are used throughout its life.

Recommended Commissioning & Baseline Frameworks

Two structures are recommended for the underlying AGL Testing & Commissioning Manual and this Guide to share as common reference points.

Five Commissioning Levels
Level 1 — Physical VerificationIs the correct equipment installed correctly?
Level 2 — Electrical VerificationIs the electrical system safe and technically correct?
Level 3 — Functional VerificationDoes the equipment perform its intended function?
Level 4 — Performance VerificationDoes it achieve the required performance?
Level 5 — Lifecycle BaselineWhat is the verified starting condition for future asset management?
Six-Level Baseline Hierarchy
Level 1 — Asset BaselineIdentity + location + condition
Level 2 — Component BaselineFixture, transformer, cable, sign, PAPI, CCR
Level 3 — System BaselineSeries circuit, CCR, ALCMS, control
Level 4 — Performance BaselineElectrical, photometric, functional, energy
Level 5 — Operational BaselineActual operating behaviour
Level 6 — Reliability BaselineInitial reliability assumptions and future failure history

This baseline hierarchy makes the subsequent Inspection, Testing, Preventive Maintenance, Failure Analysis and Asset Condition Assessment divisions much stronger.

Frequently Asked Questions

Quick answers about Commissioning & Baseline Asset Performance in the AGL Asset Lifecycle Guide.

Q1What is Division 07 — Commissioning & Baseline Asset Performance in the AGL Asset Lifecycle Guide?

Division 07 is the technical gateway between handover and operations. It covers 19 topics on commissioning verification, electrical/photometric/functional baselines, CCR/transformer/cable/fixture/PAPI/sign/ALCMS baselines, energy and operational baselines, initial reliability, condition assessment, baseline records and asset acceptance.

Q2What is commissioning verification?

Commissioning verification confirms that the installed AGL system satisfies the approved design, specifications and commissioning requirements. It checks items such as correct equipment, location, configuration, circuit, wiring and connections.

Q3Which baselines are established at commissioning?

Division 07 covers electrical, photometric, functional, energy, operational and initial reliability baselines. It also has baselines for CCRs, transformers, cables, fixtures, PAPI, signs and ALCMS.

Q4What does the electrical baseline measure?

It establishes the initial measured electrical condition of the AGL system, including voltage, current, insulation resistance, earth resistance, continuity and circuit resistance.

Q5What is the photometric baseline?

It establishes the initial optical performance of the AGL system, covering intensity, photometric distribution and beam characteristics. It is one of the strongest links to the AGL Photometry Testing Manual.

Q6Why is the initial reliability baseline different from other baselines?

At commissioning there may not yet be enough operational history to calculate meaningful long-term failure statistics. The initial reliability baseline therefore records the starting point for future analysis, such as equipment type, manufacturer, model, criticality, expected service life and manufacturer-supplied reliability data.

Q7How are baseline results recorded?

Every baseline measurement should have a controlled test record with asset ID, equipment, test type, date, location and operating condition. The baseline performance report then consolidates the results into a single controlled lifecycle document.

Q8When should acceptance criteria be defined?

Asset acceptance criteria should be defined before commissioning begins. They cover installation, electrical, functional, photometric and control and monitoring compliance, and after successful commissioning the asset moves to a defined lifecycle status.

Go Further

Commission the Asset. Set the Baseline. Build AGL Expertise.

Effective AGL asset management starts with a commissioning baseline that every future inspection and test is measured against.

Learn how electrical, photometric and functional baselines, acceptance criteria and post-commissioning asset status connect across the complete AGL asset lifecycle.

Turn technical reference knowledge into a deeper understanding of how AGL assets are planned, managed, operated and sustained throughout their lifecycle.

Commission better. Set the baseline. Build technical capability.

Take Your AGL Knowledge Further

Build structured knowledge in:

AGL Fundamentals Commissioning Verification Electrical Baseline Photometric Baseline Functional Baseline Baseline Test Records Asset Acceptance Criteria Post-Commissioning Status

Talk to Precision AGL Academy

Follow the Academy