What is civil tolerance?

How far the civil works under a light may differ from the design — position, level, orientation and depth — and how each is measured, accepted or corrected before grouting sets and before surfacing.

DESIGN VS AS BUILT design, as built, then accept or rectify WHAT HAS A TOLERANCE each dimension affects the light above it DESIGN position, level, orientation AS BUILT measured on site before surfacing CHECKED accept or rectify CHECK BEFORE GROUT SETS AND BEFORE SURFACING POSITION offset from the line and spacing along it LEVEL height against the finished pavement or ground ORIENTATION base index mark aligned to the line axis DEPTH, FOOTING trench cover, duct and foundation dimensions SIX CIVIL STEPS · IN ORDER 1 SET OUT survey the line and mark each position and level 2 EXCAVATE dig to design depth; locate and protect existing services 3 PLACE set the base can or foundation at design position 4 MEASURE position, level and orientation against the design 5 FIX, CURE grout or concrete; re-check before it sets 6 RECORD as-built survey, before surfacing and after
design: position and level
as built: measured on site
checked: accept or rectify
moving dot: out of tolerance is rectified, then passes the gate
dashed band: permitted tolerance
The Fact Construction practice

Civil tolerance is the permitted difference between the design and what is built in the civil works that carry the lights. A fixture can only be aligned and levelled as well as its base allows, so the base is measured as built against the design position, level and orientation, and is either accepted or rectified while that is still easy to do.

The checks come before the base is grouted or concreted in and again before surfacing or overlay buries the evidence. A base set too high can be a hazard, one set too low collects water and debris, and one out of position breaks the pattern spacing. Excavation is done under the airport’s permit-to-work, with existing cables and services located and protected before anything is dug.

  1. Set out. Survey the line and mark each position and level from the design drawings.
  2. Excavate. Dig to the design depth, locating and protecting existing cables and services first.
  3. Place. Set the base can or foundation at the design position and orientation.
  4. Measure. Check position, level and orientation against the design before it is fixed.
  5. Fix & cure. Grout or concrete the base, re-checking before it sets and again after.
  6. Record. Take as-built measurements before surfacing and after, and log any rectification.
PurposeMake sure the civil works under each light are close enough to the design to allow correct alignment
Order of workSet out, excavate, place, measure, fix and cure, record
SafetyExcavation under permit with existing services located and protected
DimensionsPosition, level, orientation, trench depth and foundation dimensions
RecordsAs-built measurements, rectification and records
ReferenceFAA AC 150/5340-30 · FAA AC 150/5370-10 (Item L-125) · ICAO Doc 9157 Pt 5 · base-can manufacturer instructions
Schematic — simplified and not to scale. Tolerance values for position, level, orientation and depth depend on the project specification, the design, the regulator and the manufacturers’ instructions; always follow your site’s permit-to-work procedure.
Entry 17 · Fixture alignment Entry 20 · Civil inspection

Frequently Asked Questions

Q1What is civil tolerance in airfield ground lighting?

It is the permitted difference between the design and what is actually built in the civil works that carry the lights: base can position and level, spacing along the line, orientation, trench depth and foundation dimensions. Work inside the tolerance is accepted, and work outside it is corrected.

Q2Why does civil tolerance matter for a light?

A light can only be aligned and levelled as well as the base beneath it allows. A base set too high can be a hazard or be struck by vehicles, one set too low collects water and debris, and a base out of position or rotated breaks the spacing and aiming of the pattern.

Q3What is usually given a tolerance?

Position across the line and spacing along it, level relative to the finished pavement or ground, orientation of the base or index mark, depth and cover of ducts and trenches, and foundation dimensions for elevated lights and signs. The design drawings and specification define each one.

Q4When should tolerance be checked?

Before the base is grouted or concreted in, so errors can still be corrected, and again before surfacing or overlay work buries the evidence. A check after the pavement is finished confirms the as-built condition for the record.

Q5What happens if something is outside tolerance?

It is rectified or referred to the designer and the airport for a decision, and the outcome is recorded. A small error corrected at the base stage is far cheaper than one found after the pavement is laid.

Q6What tolerance values apply?

Values come from the project specification, the design, the regulator, the applicable standard and the manufacturer's instructions. Always use the figures for your site rather than a generic number.

Precision AGL Academy

See It. Understand It. Then Learn How to Engineer It.

Recognising an AGL system visually is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how each light, sign and circuit works as part of a complete airport lighting system, not just as an isolated diagram.

See. Understand. Apply. Engineer.