What is circuit expansion?

Adding fixtures, transformers and cable to an existing series circuit — only as far as the CCR’s rating allows.

SERIES CIRCUIT · EXPANSION (ADDING A NEW SECTION) CHECK THE LOAD · TIE IN ONLY WHEN DE-ENERGISED CCR LOAD CCR RATING EXISTING NEW SPARE EXISTING + NEW MUST STAY WITHIN THE RATING load = lamps + transformers + cable keep spare capacity for the future CCR T1 T2 T3 T4 T5 EXISTING CIRCUIT NEW SECTION 1 TIE-IN MADE DE-ENERGISED, LOCKED OUT HEADROOM AVAILABLE EXTEND THE CIRCUIT Then re-test and record a new baseline NO HEADROOM NEW CIRCUIT OR LARGER CCR Zone the new lighting separately SCHEMATIC · LOOP SHORTENED · NOT TO SCALE
existing circuit
new section
lamp lit
The Fact Series circuit design

Circuit expansion is adding fixtures, isolation transformers or cable to an existing series circuit, such as when a taxiway is extended. Because every addition is in series on the same loop, it adds to the circuit’s load and cable length.

The total load after expansion must stay within the rating of the CCR, with spare capacity left. The new section is tied in only with the circuit isolated, locked out and proved dead, then the extended loop is tested and its readings recorded as the new baseline. If there is no headroom, the new lighting goes on a new circuit or a larger CCR.

  1. Check headroom. Existing load plus the addition must stay within the CCR rating, and the longer loop within its output voltage.
  2. Decide. Extend the circuit, or use a new circuit or CCR if there is no headroom.
  3. Isolate. CCR off, locked out and tagged; confirm the circuit is dead.
  4. Connect. Tie the new cable and transformers into the loop in series.
  5. Test. Continuity, insulation, and rated current with every fixture lit.
  6. Record. New baseline readings; update drawings and the zone map.
Purpose Add lighting to an existing series circuit
Key check Total load within the CCR rating, with spare capacity
Connection Made de-energised, locked out and proved dead
After connecting Continuity and insulation tests; rated current check
No headroom New circuit or larger CCR
Reference ICAO Doc 9157 Pt 5; FAA AC 150/5340-30
Schematic — loop shortened for clarity. Isolation means the full sequence shown in Entry 10, Circuit Isolation, including earthing at the work point. Always follow your site’s isolation and permit-to-work procedure and the equipment manufacturer’s instructions; fault-finding methods and acceptable values are set by the applicable standard and the commissioning record.
Entry 15 · Circuit zoning Entry 17 · Circuit termination

Frequently Asked Questions

Q1What is circuit expansion in airfield lighting?

Adding fixtures, isolation transformers or cable to an existing series circuit, for example when a taxiway is extended or extra lights are installed, instead of building a new circuit for them.

Q2What must be checked before expanding a circuit?

That the total load after the addition, made up of the lamps or LEDs, the isolation transformers and the extra cable, is still within the rating of the CCR serving the circuit, with spare capacity left. The extra cable and transformers also raise the voltage the CCR must supply, which must stay within its output voltage capability, and the circuit must keep operating at the same current and brightness steps.

Q3What if the CCR has no spare capacity?

The new lighting goes on a new circuit, normally with its own CCR, or the existing CCR is replaced with a larger one. Putting the new fixtures on their own zone also keeps faults and control separate.

Q4How is the new section connected?

With the circuit isolated, locked out and proved dead. The new primary cable is jointed or connected into the loop, with each new transformer connected in series, following the manufacturer's instructions and the site's permit-to-work procedure.

Q5What testing follows an expansion?

Continuity and insulation resistance tests on the extended loop, then a check that the circuit runs at its rated current and every new fixture lights at each brightness step. The results are compared with the design values.

Q6Why is the baseline updated?

Adding cable and transformers changes the loop's resistance and loading, so the old commissioning values no longer apply. The new readings are recorded as the baseline, and drawings and the zone map are updated, so later tests and fault finding compare against the right figures.

Precision AGL Academy

See It. Understand It. Then Learn How to Engineer It.

Recognising an AGL system visually is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how each light, sign and circuit works as part of a complete airport lighting system, not just as an isolated diagram.

See. Understand. Apply. Engineer.