In what order does the lighting change from normal to LVP and back?

Going in, the lights are checked and the standby supply made ready before LVP are in force. Coming back, ATC cancels only after visibility has stayed better for a margin and a delay.

NORMAL TO LVP AND BACKNORMALStep follows the step tableStop bars as ATC needs themCAT II/III-only lights maybe off or at a low stepPREPARATIONATC declares preparationLamps, circuits, interlockschecked and read backStandby power made readyLVP IN FORCEFull CAT II/III pattern litStop bars on where in useCentreline off beyond a lit barStep follows the RVR tableSTAND-DOWNVisibility better: margin + delayATC cancels LVPStop bars back to normal useSteps return; state confirmedTRIGGERCHECKEDCANCELBACK TO NORMALDOWNGRADE, WHILE IN FORCEIf serviceability falls below the minimum, the category or minima are reduced and ATC is told.
normal
changeover phase
LVP in force
The Fact Mode changeover

A changeover is a sequence, not a switch. Each phase is declared by ATC and each state is confirmed before the next one starts. The aim is that no light, interlock or standby supply is left in an unknown state while the aerodrome is working to low-visibility minima.

The stop bars and the taxiway centreline are the part most often got wrong. A lit stop bar means stop, so the green lights beyond it must be off, and no changeover may leave the two out of step.

  1. Trigger. Visibility or cloud base reaches the limit set in the aerodrome’s LVP document. ATC decides, not the lighting.
  2. Prepare. ATC declares the preparation phase. The standby power is made ready and the critical areas are protected.
  3. Check. Lamps, circuits and interlocks are read back from the control system. A fault found now is dealt with before LVP are in force.
  4. Put in force. The LVP configuration is set: the full CAT II/III approach pattern, stop bars at the holding positions in use, and the step from the RVR table.
  5. Hold the interlock. The taxiway centreline beyond a lit stop bar stays off. ATC extinguishes a bar only to clear a movement.
  6. Monitor and downgrade. If serviceability falls below the minimum, the category or minima are reduced and ATC is told.
  7. Stand down. Visibility improves and stays better for a margin and a delay. ATC cancels LVP.
  8. Return and confirm. Stop bars return to normal use and the steps return to the table for the conditions. The state reached is confirmed against the state requested and logged.
Confirm each step

Read back the state of the lights, circuits and interlocks, and log it, before the next phase.

Assume the command worked

A command sent is not a state reached. A lost link or a failed circuit would go unseen until an aircraft needs the lights.

PurposeMove the lighting between modes safely and in order
TriggerSet by the aerodrome: preparation starts at a higher RVR or cloud base, and LVP are commonly in force near RVR 550–600 m or low cloud
PhasesPreparation, in force, downgrade and stand-down
InterlockCentreline beyond a lit stop bar is off
PowerStandby supply ready, with a short switch-over
ControlATC declares; the system executes and confirms
RecordEach change logged in the event log
AuthorityThe approved LVP document and aerodrome manual
Schematic. The order, the triggers and the light list are an example of the usual arrangement. Your aerodrome’s approved LVP document and the regulator decide the real sequence, so confirm against them.
Entry 42 · Intensity step selection by visibility and day/night Full Index · Division 17

Frequently Asked Questions

Q1What is the mode changeover sequence?

It is the ordered set of steps by which the airfield lighting moves from normal operations to the Low-Visibility Procedures configuration and then back again. ATC declares the phases, the lighting control system carries out the configuration and reports status, and the order and values come from the aerodrome's approved LVP document.

Q2What happens in the preparation phase?

ATC declares the preparation phase. The lights and critical areas are checked and the standby power is made ready, so that the full configuration can be put in force with every item healthy and monitored. Nothing is assumed: the status of lamps, circuits and interlocks is read back.

Q3Why are the stop bars and taxiway centreline interlocked during changeover?

A lit stop bar means stop, so the green centreline lights beyond it must be off. The interlock holds that rule on every change of mode, so a changeover never leaves green lights lit beyond a lit stop bar. ATC extinguishes a bar only to let an aircraft move.

Q4What if a light or circuit fails while LVP are in force?

If serviceability falls below the minimum for the operation, the category or minima are reduced and ATC is told. The lighting does not quietly carry on at a level the aerodrome has not approved. The minimum serviceability levels come from the approved LVP document and the regulator.

Q5Why does the return to normal wait?

Stand-down normally needs visibility to stay better for a margin and a delay before ATC cancels LVP. That stops the aerodrome switching in and out of LVP with every reading, and it is the same idea as the hysteresis in the RVR step table.

Q6Who controls the changeover, ATC or the system?

ATC declares each phase. The lighting control system then sets the lights, intensity steps and interlocks, and shows ATC and maintenance the state reached. The system should confirm the state reached against the state requested, and record the change in its event log. Follow the aerodrome's approved procedure for who does what.

Precision AGL Academy

See It. Understand It. Then Learn How to Engineer It.

Recognising an AGL system visually is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how each light, sign and circuit works as part of a complete airport lighting system, not just as an isolated diagram.

See. Understand. Apply. Engineer.