What is excavation safety?

Digging safely around buried AGL cables and services: finding them first, protecting the opening and the people in it, and reinstating the ground.

EXCAVATION SAFETY · LOCATE, PROTECT, DIG, REINSTATE 1 LOCATE Drawings, detector, marking 2 PROTECT Barriers, support, access 3 DIG Hand dig near services 4 REINSTATE Backfill, compact, restore CROSS-SECTION VIEW SHORED SIDESSAFE ACCESS EXPOSED CABLETREAT AS LIVE HAND DIG NEAR SERVICES · NEVER ASSUME A CABLE IS DEAD OTHER SERVICELOCATED & MARKED LOCATE & MARK FIRST EDGE BARRIERS SPOIL SET BACKFROM THE EDGE 1234 BACKFILLED · COMPACTED · SURFACE REINSTATED · AREA CLEARED · THEN REPORTED CLEAR SCHEMATIC · DEPTHS, SUPPORT AND CLEARANCES ARE SET BY THE SITE’S RULES AND THE DIG PERMIT
barrier / other service
trench / cable
located / checked
The Fact Safety principle

AGL cables and ducts are buried, and airfield lighting series circuits carry a lethal current at up to several thousand volts, so digging near them can be lethal if a cable is struck. Excavation therefore starts before the spade: drawings are checked, services are located with a detector and marked on the surface, and the dig is planned and permitted. Every cable is treated as live unless it has been isolated and proved dead under the site procedure.

The opening is then made safe. Edges are barriered, sides are sloped or supported, safe access is provided, and spoil is set back so it neither loads the edge nor becomes FOD. Near services the work is done by hand. If an unknown or damaged service is found, work stops and it is reported. At the end the cable condition is checked, the trench is backfilled in layers and compacted, the surface is reinstated and the area is cleared before it is reported clear.

HazardsLive cables, collapse, FOD
Before diggingDrawings, locate, mark, permit
CablesTreated as live
Near servicesHand dig, no machines
OpeningBarriered, supported, access
SpoilSet back from the edge
Unknown serviceStop, keep clear, report
ReferenceSite dig permit and excavation rules; FAA AC 150/5370-2 (operational safety during construction); ICAO Annex 14 (aerodrome maintenance) for background
Awareness schematic only, not a working procedure. Dig permits, safe distances, trench depth and support requirements, isolation and permit-to-work arrangements come from the airport’s procedures, local regulations and your employer’s permit to work.
Entry 13 · FOD prevention Entry 15 · Cable-work safety

Frequently Asked Questions

Q1What is excavation safety in AGL work?

The set of precautions used when digging near airfield lighting cables, ducts and other buried services. It covers finding services before digging, protecting the opening and the people working in it, digging carefully near services, and restoring the ground afterwards.

Q2Why is every buried AGL cable treated as live?

Airfield lighting series circuits carry a constant current at up to several thousand volts, so a damaged cable can be lethal. A cable is not assumed to be dead because it looks old or unmarked. It is treated as live unless it has been isolated and proved dead under the site’s procedure.

Q3Why locate and mark services before digging?

Cables and ducts are not always where the drawings show, and other services such as fuel, water, data and power may run nearby. Drawings are checked, services are located with a detector and marked on the surface, and the dig plan is agreed before the ground is opened. A detector may not pick up a cable that is switched off, so the survey is confirmed by hand-dug trial holes where the site rules require.

Q4How are trench collapse risks controlled?

Trench sides can collapse without warning. Depending on depth and ground, they are sloped back or supported with shoring, edges are barriered, safe access such as a ladder is provided, and nobody works in an unsupported trench. The site’s rules set what is required.

Q5Why keep spoil back from the trench edge?

Spoil piled at the edge adds load that can bring the side down, and loose soil and stone are FOD risks on airfield pavements. Spoil is set back, contained, and removed or reused as the work allows.

Q6What if an unknown cable or service is found or damaged?

Stop work and keep everyone clear. Do not touch or move the cable. Report it to the supervisor and, through the site procedure, to airport operations, and wait for it to be identified and made safe before work continues.

Precision AGL Academy

See It. Understand It. Then Learn How to Engineer It.

Recognising an AGL system visually is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how each light, sign and circuit works as part of a complete airport lighting system, not just as an isolated diagram.

See. Understand. Apply. Engineer.