What is CCR maintenance?

Keeping the constant current regulator clean, cool, tight and accurate, so every light on its series circuit receives the right current at every brightness step.

CCR IN SERVICE · WHAT CCR MAINTENANCE CHECKSCCR 4.1 ASTEP 3 · NORMALVENTS & FILTERCONTROLLER & ALARMSINPUTOUTPUT · HIGH VOLTAGEEARTHTO SERIES CIRCUITMAINS1ISOLATE & PROVE DEADlock out input, prove dead, discharge2CLEAN & COOLenclosure, filters, fans, moisture3TERMINATIONStight, clean, no heat discolouration4CONTROLS & ALARMSdisplay, steps, local and remote5OUTPUT CHECKcurrent per step against rating6RECORD & RESTOREreadings, defects, return to serviceISOLATE · LOCK OUT · PROVE DEAD BEFORE THE CABINET IS OPENEDNEVER LEAVE AN ENERGISED OUTPUT OPEN-CIRCUIT
output / terminations
isolation / mains
hazard / defect
cooling / display
earth
The Fact Maintenance practice

A constant current regulator (CCR) holds the current in an airfield series circuit steady, whatever the number of lights or the supply voltage. CCR maintenance keeps it able to do that: the enclosure, vents, filters and fans are kept clean and cool, the input and output terminations are kept tight and free of heat damage, and the controls, display and alarms are proved to work locally and remotely.

A CCR works at high voltage and drives a current loop, so the work is hazardous. The regulator is isolated, locked out and proved dead before the cabinet is opened, and the output circuit is never left open while energised. Output current is then measured at each brightness step and compared with the rating and the commissioning baseline.

  1. Plan. Confirm the CCR and circuit, agree the outage with ATC, and obtain the permit-to-work.
  2. Isolate. Switch off, lock out the input supply, prove dead and let stored energy discharge.
  3. Inspect & clean. Enclosure, seals, filters, fans, dust and moisture.
  4. Check terminations. Tightness, cleanliness, discolouration and earth connection.
  5. Test. With the CCR re-energised under the permit, check controls, alarms, local and remote operation, then output current at each step.
  6. Record & restore. Log readings and defects, close up, return to service and confirm the circuit is lit.
Purpose Keep the CCR reliable, cool and accurate for its series circuit
Circuit state Isolated, locked out and proved dead before opening
Checks Enclosure, cooling, terminations, controls, alarms, output current
Typical defects Clogged filter, failed fan, loose or hot terminal, moisture, dead alarm
Key hazard High output voltage; never open-circuit the energised output
Reference ICAO Annex 14 Vol I Ch. 10 · ICAO Doc 9157 Pt 5 · IEC 61821 · FAA AC 150/5345-10 · FAA AC 150/5340-26
Schematic — a generic CCR drawn for clarity; layouts differ by manufacturer and model. Inspection intervals, test values and acceptance criteria depend on the airport’s maintenance programme, the manufacturer’s manual and the applicable standard. Only trained, authorised personnel should work on a CCR, always under the site permit-to-work and lockout procedure.
Entry 18 · Sign maintenance Entry 20 · Approach-light maintenance

Frequently Asked Questions

Q1What is CCR maintenance in airfield lighting?

The planned inspection, cleaning, testing and repair of the constant current regulator that supplies a series lighting circuit, covering its enclosure, cooling, terminations, controls, alarms and output performance.

Q2Why must a CCR never be left open-circuit while energised?

A CCR drives a fixed current through the circuit. With the output open, it tries to force that current through an infinite resistance and the output voltage can rise to dangerous levels. Many regulators have open-circuit protection, but it is not a safeguard for people working on the circuit. The circuit is isolated and the regulator switched off and locked out before any output connection is disturbed.

Q3What is checked before the cabinet is opened?

That the correct CCR and circuit are identified, the permit-to-work is in place, the input supply is isolated and locked out, and the equipment is proved dead with a tester that has itself been proved. Stored energy is allowed to discharge before work starts.

Q4How is CCR output checked?

With the circuit energised under the site procedure, output current is compared against the rated value for each brightness step using calibrated instruments, and the readings are compared with the commissioning baseline.

Q5What are the most common CCR faults found during maintenance?

Blocked filters or failed fans causing overheating, loose or discoloured terminations, moisture and dust inside the cabinet, worn contactors, and alarms or remote-control links that no longer work.

Q6How often should a CCR be maintained?

The interval comes from the airport maintenance programme, the manufacturer instructions and the national authority guidance, and is usually shorter in hot, dusty or humid locations.

Precision AGL Academy

See It. Understand It. Then Learn How to Engineer It.

Recognising an AGL system visually is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how each light, sign and circuit works as part of a complete airport lighting system, not just as an isolated diagram.

See. Understand. Apply. Engineer.