What is cable inspection?

A visual and physical check of the cable route and every point you can reach on it, done before the electrical tests, so damage and moisture are found before they become faults.

CABLE ROUTE · WHAT AN INSPECTION CHECKS, IN ORDERGROUND LEVELEARTH BONDwater in pitDUCT · SHEATHcorroded connectorMARKERMARKERINSPECTION RECORDphoto · location · action1243561 · Route & markers2 · Pits & manholes3 · Ducts & cable4 · Joints & connectors5 · Earthing & bonding6 · Record & act
primary cable
pit / manhole
duct / sheath
earth bond
defect found
The Fact Maintenance practice

Most AGL cable is buried, so a cable inspection concentrates on the places that can be seen: the route above the cable, the pits and manholes, joints and connectors, any exposed duct or sheath, and the earth bonds. It is a hands-on check and a regular part of the maintenance programme. Walking the route can be done first, but pits and connectors are opened only with the circuit isolated, locked out and proved dead.

Inspection often finds the cause of a poor test reading, such as water standing in a pit or a corroded connector, which is why it comes first. Each defect is photographed and logged against its circuit and location so the next inspection can show whether it is getting worse.

  1. Isolate. Circuit off, locked out and proved dead before any pit or connector is opened.
  2. Walk the route. Check markers and the ground above for settlement, digging or new works.
  3. Open pits. Look for water, silt, debris and damaged lids. Treat deep pits and manholes as confined spaces.
  4. Check duct and sheath. Cuts, crushing, heat damage, strain at bends.
  5. Check joints, connectors and earthing. Corrosion, looseness, heat marks, cracked sealing, missing bonds.
  6. Record & act. Photograph, log, raise repairs, restore and re-test where needed.
Purpose Find damage and moisture before they cause a fault
Circuit state Isolated and locked out before any pit or connector is opened
Check points Route, pits, joints, connectors, ducts, earthing
Typical defects Water in pits, corroded connectors, damaged sheath
Record Dated photo, location, circuit and action
Reference ICAO Doc 9157 Pt 5; FAA AC 150/5340-26
Schematic — one cable run with typical features, drawn for clarity. Inspection intervals, checklists and defect categories are set by the airport’s maintenance programme and the applicable standard; always follow your site’s permit-to-work procedure.
Entry 10 · Transformer inspection Entry 12 · Cable testing

Frequently Asked Questions

Q1What is cable inspection in airfield lighting?

A visual and physical check of the cable route and the accessible points along it, including markers, pits, joints, connectors, ducts, sheath and earthing, carried out as part of routine maintenance.

Q2Why is inspection done before testing?

It finds obvious causes, such as water in a pit or a corroded connector, and makes sure the circuit is safe to test. Findings also show where to focus the electrical tests.

Q3Does the circuit have to be isolated?

Yes for opening pits and handling connectors. The circuit is switched off, locked out and proved dead under the site permit-to-work procedure before any work starts.

Q4What are the common defects?

Water or silt in pits, corroded or loose connectors, damaged sealing, cuts or crushing of the sheath or duct, and missing or corroded earth bonds.

Q5How are findings recorded?

Each defect is logged against the circuit and location with a dated photograph and the action taken, so later inspections can show whether it is stable or getting worse.

Q6How often should cables be inspected?

The interval is set by the airport’s maintenance programme and the national authority’s guidance, and may change with the age and condition of the circuit.

Q7Are there special hazards in pits and manholes?

Yes. Deep pits and manholes can be confined spaces with standing water, silt, poor air or gas, and may sit beside live cables on other circuits. Follow the site's confined-space and permit-to-work rules, and never enter a flooded pit.

Precision AGL Academy

See It. Understand It. Then Learn How to Engineer It.

Recognising an AGL system visually is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how each light, sign and circuit works as part of a complete airport lighting system, not just as an isolated diagram.

See. Understand. Apply. Engineer.