What is a cable entry?

Where an AGL cable passes through the wall of a base can, pit or housing — formed at the designed position, with smooth bushed edges, a gentle bend, a seal around the cable and a slack loop inside, so the enclosure stays dry and the sheath is not cut.

PIT ENTRY · SECTION duct to pit wall, sealed entry, slack loop inside ENTRY DETAIL · SECTION through the wall: bush, seal, gentle bend GROUND PIT LID PIT DUCT SLACK LOOP, GENTLE BEND CONN UNUSED ENTRY BLANKED OFF SEALED ENTRY GROUND / BEDDING INSIDE THE PIT WALL DUCT SEAL AROUND CABLE BUSHED EDGE GENTLE BEND NOT BELOW MIN. BENDING RADIUS SIX ENTRY CHECKS · IN ORDER 1 POSITION at the designed entry, duct in line with it 2 OPEN opening or sleeve formed clean, cut edges made smooth 3 BUSH bush, grommet or gland fitted so the sheath is safe 4 PULL cable through without strain, bend radius kept 5 SEAL sealed around the cable as specified, unused ones blanked 6 SLACK, MARK slack loop inside, cable identified, entry recorded
seal and connector
duct and sleeve
cable, bush and slack loop
wall and ground
The Fact Installation & construction

A cable entry is the point where an AGL cable passes through the wall of a base can, pit, sign or equipment housing. It is formed at the position the design provides, with smooth, bushed edges, and sealed around the cable so the enclosure stays dry and the cable is protected where it crosses from the ground into the enclosure.

The entry is a small detail with a long life. A sharp edge slowly cuts the sheath, and an open or poorly sealed entry lets in water, soil and pests that end up around connectors and terminations as earth faults. Bring the cable in with a gentle bend, leave a slack loop inside, blank off any unused entry and identify the cable. Treat any cable as live until the circuit has been isolated, locked out and proved dead, and work to the airport’s permit-to-work.

  1. Position. Use the entry the design provides and bring the duct in line with it.
  2. Open. Form the opening or sleeve cleanly and smooth any cut edges.
  3. Bush. Fit the bush, grommet or gland so the sheath has a smooth path.
  4. Pull. Bring the cable through without strain and keep to its minimum bending radius.
  5. Seal. Seal around the cable as specified and blank off unused entries.
  6. Slack, mark and record. Leave a gentle slack loop, identify the cable and record the entry.
Purpose Let the cable cross the wall of a pit, base can or housing, protected and sealed
Position At the entry provided by the pit or base-can design
Edge Smooth, bushed or glanded so the sheath is not cut
Seal Sealed around the cable as specified; unused entries blanked
Inside Gentle bend and slack loop, within the minimum bending radius
Reference FAA AC 150/5340-30 · AC 150/5370-10 (Items L-108, L-110) · AC 150/5370-2 (construction safety) · ICAO Doc 9157 Pt 5
Schematic — simplified and not to scale. Entry type, sleeve or gland, sealing material, position and unused-entry blanking depend on the pit, base can or housing and its manufacturer; follow the design drawings, the manufacturer’s data and your site’s permit-to-work procedure.
Entry 11 · Cable crossing Entry 13 · Connector installation

Frequently Asked Questions

Q1What is a cable entry in airfield ground lighting?

A cable entry is the point where an AGL cable passes through the wall of a base can, pit, sign or equipment housing. It is formed at the position the design provides, with smooth edges, and sealed around the cable so the cable is protected where it crosses from the ground into the enclosure.

Q2Why does a cable entry have to be sealed?

An open entry lets water, soil and dirt run into the pit or base can, and can give rodents and insects a way in. Water around connectors and terminations is a common cause of insulation faults. The seal keeps the enclosure dry and clean, and the method and material are set by the design and the manufacturer.

Q3Why must the edges of the entry be smooth or bushed?

The cable sheath is pulled or pushed past the edge of the opening and then sits against it for years. A rough or sharp edge can cut or wear the sheath, which later shows up as an earth fault. A bush, grommet or gland gives the cable a smooth, supported path through the wall.

Q4Why leave slack in the cable just inside the entry?

Slack, usually as a gentle loop, lets the cable move with ground settlement and temperature without pulling on the entry or the connector, and leaves enough length to re-terminate or replace a fixture later. The loop must stay within the cable’s minimum bending radius.

Q5What should be done with unused entries?

Unused entries are blanked or plugged as the design and manufacturer specify, so they do not become a route for water or pests. Do not leave a knock-out or sleeve open, and do not make a new opening in a pit or base can except as the design allows.

Q6What should be checked before the entry is covered or the pit closed?

Check that the entry is at the designed position, the edges are smooth or bushed, the cable has a gentle bend and is not strained, the seal is complete around the cable, unused entries are blanked, slack is left inside and the cable is identified. Treat any cable as live until the circuit has been isolated, locked out and proved dead, and work to the permit-to-work.

Precision AGL Academy

See It. Understand It. Then Learn How to Engineer It.

Recognising an AGL system visually is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how each light, sign and circuit works as part of a complete airport lighting system, not just as an isolated diagram.

See. Understand. Apply. Engineer.